— March 2019: installation of standard offices by the general contractor,
— March/April 2019: site installations by the general contractor,
— 20 April to 31.8.2019: works in the MEPs’ areas of the ASP and the WIB (about 70 000 m2),
— supervision of building sites to be undertaken by the security subcontractor of the general contractor on the instructions of DG SAFE,
— offices,
— relocation of existing furniture and IT equipment (furniture and IT contractors under the supervision of the general contractor),
— changing of floor and wall coverings, painting of ceilings,
— changing of lighting,
— adaptation of floor boxes,
— installation of new furniture (furniture contractor under the supervision of the general contractor),
—— corridors, lift hallways, walkways,
— relocation of existing furniture (furniture contractor under the supervision of the general contractor),
— changing of floor and wall coverings, painting of ceilings,
— installation of new furniture (furniture contractor under the supervision of the general contractor),
— change of signage (new signage possibly provided by new signage contractor and installed by the general contractor).