172984-2026 - Ergebnis
Dänemark – Elektrische Maschinen, Geräte, Ausstattung und Verbrauchsartikel; Beleuchtung – LOT 1 - Variable Shunt Reactors for outdoor installation for SLF02 and NEA
OJ S 50/2026 12/03/2026
Bekanntmachung vergebener Aufträge oder Zuschlagsbekanntmachung – Standardregelung
Lieferleistungen
1. Beschaffer
1.1.
Beschaffer
Offizielle BezeichnungEnerginet Eltransmission A/S
E-Mailprocurement@energinet.dk
Rechtsform des ErwerbersÖffentliches Unternehmen
Tätigkeit des AuftraggebersMit Strom zusammenhängende Tätigkeiten
2. Verfahren
2.1.
Verfahren
TitelLOT 1 - Variable Shunt Reactors for outdoor installation for SLF02 and NEA
Beschreibung15 + 2 optional 400 kV 70-140Mvar - Reaktorer • Lot1 consists of 5 units on 400kV, 70-140Mvar 63kA • Lot2 consists of 5 + 1 optional units on 400kV, 70-140Mvar 63kA + • Lot3 consists of 5 +1 optional units on 400kV, 70-140Mvar 80kA Variable Shunt Reactors Rated voltage Ur: 400kV Power rating: 70-140 Mvar Regulation Range: 50 % or above Type of regulation: onload (OLTC) Cooling: ONAN Maximum sound power level: 84 dB(A), prefer-ably lower, (at max. operating voltage 420 kV) Corrosion Protection: C5VH or above Max. operating voltage Umax: 420 kV Frequency: 50 Hz Magnetic characteristic: The core must be linear up to 1.5 times rated voltage.
Kennung des Verfahrens6feb2f6f-2e21-4560-9e47-8afba14ee19d
Vorherige Bekanntmachung489180-2018
Interne Kennung24/10093
VerfahrensartVerhandlungsverfahren mit vorheriger Veröffentlichung eines Aufrufs zum Wettbewerb/Verhandlungsverfahren
Das Verfahren wird beschleunigtnein
2.1.1.
Zweck
Art des AuftragsLieferleistungen
Haupteinstufung (cpv): 31000000 Elektrische Maschinen, Geräte, Ausstattung und Verbrauchsartikel; Beleuchtung
Zusätzliche Einstufung (cpv): 31170000 Transformatoren
2.1.2.
Erfüllungsort
PostanschriftSøndre Molgervej 30  
StadtHorsens
Postleitzahl8700
Land, Gliederung (NUTS)Sydjylland (DK032)
LandDänemark
Zusätzliche InformationenOne (1) reactor to be delivered to: Station Molger Søndre Molgervej 30 8700 Horsens
2.1.2.
Erfüllungsort
PostanschriftTisetvej 74A  
StadtMårslet
Postleitzahl8320
Land, Gliederung (NUTS)Sydjylland (DK032)
LandDänemark
Zusätzliche InformationenOne (1) reactor to be delivered to: Station Ny Malling Tisetvej 74A 8320 Mårslet
2.1.2.
Erfüllungsort
PostanschriftElvej 6  
StadtTrige
Postleitzahl8380
Land, Gliederung (NUTS)Sydjylland (DK032)
LandDänemark
Zusätzliche InformationenTwo (2) reactors to be delivered to: Station Trige Elvej 6 8380 Trige
2.1.2.
Erfüllungsort
PostanschriftHønnerupvej 48  
StadtGelsted
Postleitzahl5591
Land, Gliederung (NUTS)Fyn (DK031)
LandDänemark
Zusätzliche InformationenOne (1) option for a reactor to be delivered to: Station Kingstrup Hønnerupvej 48 5591 Gelsted
2.1.2.
Erfüllungsort
PostanschriftÅvej  
StadtVordingborg
Postleitzahl4760
Land, Gliederung (NUTS)Vest- og Sydsjælland (DK022)
LandDänemark
Zusätzliche InformationenFour (4) reactors to be delivered to: Station Vordingborg Nord Åvej 4760 Vordingborg
2.1.2.
Erfüllungsort
PostanschriftNordskovvej 6  
StadtHerfølge
Postleitzahl4681
Land, Gliederung (NUTS)Østsjælland (DK021)
LandDänemark
Zusätzliche InformationenOne (1) reactor to be delivered to: Station Ringsbjerg Nordskovvej 6 4681 Herfølge
2.1.2.
Erfüllungsort
PostanschriftGl. Ribevej 110  
StadtFredericia
Postleitzahl7000
Land, Gliederung (NUTS)Sydjylland (DK032)
LandDänemark
Zusätzliche InformationenFour (4) reactors to be delivered to: Station Ny Landerupgård Gl. Ribevej 110 7000 Fredericia
2.1.2.
Erfüllungsort
PostanschriftKassøvej 22  
StadtRødekro
Postleitzahl6230
Land, Gliederung (NUTS)Sydjylland (DK032)
LandDänemark
Zusätzliche InformationenTwo (2) reactors to be delivered to: Station Kassø Kassøvej 22 6230 Røde Kro
2.1.2.
Erfüllungsort
PostanschriftVandmøllevej 10  
StadtVejen
Postleitzahl6600
Land, Gliederung (NUTS)Sydjylland (DK032)
LandDänemark
Zusätzliche InformationenOne (1) reactor option to be delivered to: Station Revsing Vandmøllevej 10 6600 Vejen
2.1.4.
Allgemeine Informationen
Der Aufruf zum Wettbewerb ist beendet
Rechtsgrundlage
Richtlinie 2014/25/EU
5. Los
5.1.
LosLOT-0001
TitelLOT1 - SLF02
BeschreibungLot1: 5 units on 400kV, 70-140Mvar
Interne Kennung24/10093
5.1.1.
Zweck
Art des AuftragsLieferleistungen
Haupteinstufung (cpv): 31000000 Elektrische Maschinen, Geräte, Ausstattung und Verbrauchsartikel; Beleuchtung
Zusätzliche Einstufung (cpv): 31170000 Transformatoren
5.1.2.
Erfüllungsort
PostanschriftÅvej  
StadtVordingborg
Postleitzahl4760
Land, Gliederung (NUTS)Vest- og Sydsjælland (DK022)
LandDänemark
Zusätzliche InformationenFour (4) reactors to be delivered to: Station Vordingborg Nord Åvej 4760 Vordingborg
5.1.2.
Erfüllungsort
PostanschriftNordskovvej 6  
StadtHerfølge
Postleitzahl4681
Land, Gliederung (NUTS)Østsjælland (DK021)
LandDänemark
Zusätzliche InformationenOne (1) reactor to be delivered to: Station Ringsbjerg Nordskovvej 6
5.1.3.
Geschätzte Dauer
Datum des Beginns23/02/2026
Enddatum der Laufzeit30/06/2030
5.1.6.
Allgemeine Informationen
Auftragsvergabeprojekt nicht aus EU-Mitteln finanziert
Die Beschaffung fällt unter das Übereinkommen über das öffentliche Beschaffungswesenja
5.1.10.
Zuschlagskriterien
Kriterium
ArtPreis
BeschreibungPrices must be stated in Appendix 3: Price List (Lot 1 doc. no. 24/10093-19, Lot2 doc. no. 24/10093-29 and Lot3 doc. no. 24/03003-39) and the defined price elements must be completed herein. Prices must be stated exclusive of VAT but inclusive of all other expenses associated with the purchase. Prices must be stated in EUR. When evaluating 'Price', the Contracting Authority will evaluate the total cost for each Lot individually, cf. the Appendix 3: Price lists (Lot 1 doc. no. 24/10093-19, Lot2 doc. no. 24/10093-29 and Lot3 doc. no. 24/10093-39). The evaluation of prices for each Lot is based on “Total price” in EUR from row 17&18 and column G in sheet “Total Eval price for each Lot Prices must be stated in EU
Kategorie des Gewicht-ZuschlagskriteriumsGewichtung (Prozentanteil, genau)
Zuschlagskriterium — Zahl40
Kriterium
ArtQualität
BezeichnungTechnical solution
BeschreibungFor the evaluation of the sub-criteria the below should be enclosed: For each Lot the tenderer should include a technical solution description which - In detail describes the proposed solution (including design, components, processes, tools to be used etc.) and - Which demonstrates how and to which degree the competitive specifications as set out by the Contracting Authority, cf. the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093- 15 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26, are fulfilled, including any advantages elements. The tenderer should be thorough and precise when describing the technical solution, including technical advantages elements and level of fulfilment, as any insecurities and discrepancies may affect the evaluation negatively. Please note that all parts of the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093-16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26, concerning sound level, e.g. section 5.3.(sound enclosure), 11 and 13.3, will be evaluated as part of the sub-criteria “Sound level” and therefore will not be included in the evaluation of “Technical solution”. Further, please note that the elements marked in yellow in the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093- 16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26 are mandatory, cf. section 2.7.1 of the present Tender Conditions, and therefore are not included in the evaluation. In the evaluation of “Technical Solution”, the Contracting Authority will emphasize the following: The extent to which the detailed technical solution supports the delivery of high performing, well designed and robust reactors considering the scope and content of the assignment, cf. the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093-16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26. In this context, the elements listed below – and the fulfilment or lack thereof – are of particular importance: • General design - the overall technical solution for the shunt reactor design, including dimensions and accessibility. • Corrosion protection (cf. 5.5 Paint and surface treatment), including whether the protection level is higher or lower than C5vh and how all parts are treated. • Core type • Weight and Size, taking into consideration how this will affect the requirements for the foundations and stations • Tap changer (if applicable) and variation range (cf. 8. Tap Changer) • Oil type (physical characteristics such as sulphur) • Bushings (cf. 7. High-voltage connections and Bushings) • FAT- and SAT-procedure (cf. 6.5 Factory Acceptance Tests and Site Acceptance tests) The characteristics stated in the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093-16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26 are considered as an acceptable level of fulfilment. An overall evaluation will be made of this sub-criteria
Kategorie des Gewicht-ZuschlagskriteriumsGewichtung (Prozentanteil, genau)
Zuschlagskriterium — Zahl30
Kriterium
ArtQualität
BezeichnungSound level
BeschreibungThe evaluation will be based on a detailed and specific technical solution for the sound level, including: - Chosen methods, - Processes and tools for guaranteed sound power level. The evaluation of guaranteed sound level (cf. section 11. Sound Level in Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093-16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26is performed in 3 steps: Step 1): a. If the guaranteed sound power level is higher than the maximum value accepted the solution will be rejected as the minimum technical requirement is not fulfilled. b. If the guaranteed sound power level is equal to or lower than the maximum value accepted, the sound level is within an acceptable range - the score is preliminary set to a value of 5 (five), and the evaluation continues to step 2. Step 2): a. If NO external sound damping method is used to obtain the guaranteed value, the evaluation continues to step 3. b. If ANY external sound damping method is used to obtain the guaranteed value, the preliminary grade is reduced depending on the extent of the applied sound damping method: i. If Sound Panels (e.g., sandwich panels) are used, 3 (three) points will be deducted. ii. If Sound Screen is used, 3 (three) points will be deducted. iii. If Sound Housing is used, 5 (five) points will be deducted. (See note *) below for further description and definition of sound damping methods.) After the preliminary grade is reduced, the evaluation continues to step 3. Step 3): a. If sound power level is EQUAL TO the maximum value accepted by the Contracting Authority, the obtained preliminary score is the result of the evaluation. b. If sound power level is LOWER than the maximum value accepted by the Contracting Authority, the final score is obtained by adding 1 (one) point to the preliminary score for every dB the guaranteed sound power level is lower than the required maximum value. The final score cannot exceed the value 10 (ten), so no extra credit will be given for sound levels more than 10 dB lower than the maximum value. *) Note Definition of type of sound damping method (Step 2b i-iii). i. Sound Panels are panels attached directly to the tank wall, only partly covering one or more sides of the tank (e.g., sandwich panels). ii. Sound Screen is attached to the tank usually covering one or more complete sides. Typically, a screen is also installed with some centimetre distance between tank and screen, so valves, jacking points etc. must be accessed through hatches in the sound screen. iii. Sound Housing is an enclosure which surrounds the main tank, and it includes a roof. A sound house typically requires a separate or specially designed foundation.
Kategorie des Gewicht-ZuschlagskriteriumsGewichtung (Prozentanteil, genau)
Zuschlagskriterium — Zahl15
Kriterium
ArtQualität
BezeichnungContract Terms
BeschreibungFor the evaluation of the sub-criteria the tenderer is allowed to propose deviations to the elements of the contract identified as competitive elements in the contract terms: • Contract Agreement (doc. no. 24/10093-11, 24/10093- 21 and 24/10093-31), • Appendix 1: General Terms and Conditions for Purchase (doc. no. 24/10093-12), • Appendix 4 Time and Payment Schedule, (doc. no. 24/10093-20, 24/10093-30 and 24/10093-40) The deviations should be enclosed in the clarification list c.f. doc. no. 24/10093-10 and be included in the spreadsheet marked “Legal clarification”. The proposed deviations should be explicit and with explanation as to why they are made. Contract terms listed in section 2.7.1 are mandatory parts and deviations to these are not accepted. The tendered assignment must be performed on the basis of the attached contract terms. The tenderer is allowed to propose explicit and well-explained deviations to the listed competitive elements and the evaluation of “contract terms” will be based on the deviations. It should be noted that any deviation might impact the score as this is dependent on the content, clarity and consequence of the deviation. The following elements are considered competitive elements: • Appendix 1: General Terms and Conditions for Purchase and, where relevant, same Clauses and Sub-Clauses in the Contract Agreements: o Clause 2 (Requirements), except for Sub-Clause 2.3, 2.5 and 2.6 o Sub-clause 4.6 (Advance payment guarantee – except for what is stated as mandatory parts of the Tender Documents, cf. Sub-Section 2.7.1 above) o Clause 9 (Time of Delivery) o Clause 11 (Intellectual property rights) o Clause 12 (Late-delivery or non-delivery) o Clause 13 (Defects and remedies) o Clause 14 (Limitation of liability) o Clause 15 (Product liability) o Clause 16 (Insurance) o Clause 17 (Indemnification) o Clause 18 (Performance guarantee – except for what is stated as mandatory parts of the Tender Documents, cf. sub-section 2.7.1 above) o Sub-Clause 20.3 (HSE requirements) o Clause 25 (Termination) • Appendix 4: Time and Payment Schedules Deviations to these elements will be included in the evaluation and it is noted that any deviations may lead to a reduction of the score depending on the content, clarity, and consequence of the deviation. In this regard it is explicitly noted that deviations which are intended to limit liability and shift the financial risk in favor of the tenderer will be of particular importance in the evaluation. If the tenderer has no deviations to the contract terms, the maximum score of 10 will be awarded. An overall evaluation will be made of this sub-criterion. Please note that a minimum score of 4 must be achieved for the tender to be compliant, cf. sub-section 2.7.1.
Kategorie des Gewicht-ZuschlagskriteriumsGewichtung (Prozentanteil, genau)
Zuschlagskriterium — Zahl15
5.1.15.
Techniken
Rahmenvereinbarung
Keine Rahmenvereinbarung
Informationen über das dynamische Beschaffungssystem
Kein dynamisches Beschaffungssystem
5.1.16.
Weitere Informationen, Schlichtung und Nachprüfung
ÜberprüfungsstelleKlagenævnet for Udbud
Informationen über die Überprüfungsfristen: Complaints regarding a candidate not being pre-qualified must be filed with The Complaints Board for Public Procurement within 20 calendar days starting the day after the contracting authority has sent notification to the candidates involved, provided that the notification includes a short account of the relevant reasons for the decision. Other complaints must be filed with The Complaints Board for Public Procurement within: 1. 45 calendar days after the contracting authority has published a contract award notice in the Official Journal of the European Union (with effect from the day following the publication date); 2. 30 calendar days starting the day after the contracting authority has informed the tenderers in question, that the contracting authority has entered into a contract based on a framework agreement through reopening of competition or a dynamic purchasing system, provided that the notification includes a short account of the relevant reasons for the decision. 3. 6 months starting the day after the contracting authority has sent notification to the candidates/tenderers involved that the contracting authority has entered into the framework agreement, provided that the notification included a short account of the relevant reasons for the decision.
Organisation, die zusätzliche Informationen über das Vergabeverfahren bereitstelltEnerginet Eltransmission A/S
Organisation, die weitere Informationen für die Nachprüfungsverfahren bereitstelltKonkurrence- og Forbrugerstyrelsen
Organisation, aus deren Mitteln der Auftrag bezahlt wirdEnerginet Eltransmission A/S
Organisation, die die Zahlung ausführtEnerginet Eltransmission A/S
Organisation, die den Auftrag unterzeichnetEnerginet Eltransmission A/S
5.1.
LosLOT-0002
TitelLOT2 - NEA_ MOL, MAL, TRI
BeschreibungLot2: 4 units plus one (1) in option on 400kV, 70-140Mvar
Interne Kennung2-1
5.1.1.
Zweck
Art des AuftragsLieferleistungen
Haupteinstufung (cpv): 31000000 Elektrische Maschinen, Geräte, Ausstattung und Verbrauchsartikel; Beleuchtung
Zusätzliche Einstufung (cpv): 31170000 Transformatoren
Optionen
Beschreibung der OptionenThe Agreement contains options regarding one (1) additional variable shunt reactor that Supplier is obligated to deliver
5.1.2.
Erfüllungsort
PostanschriftSøndre Molgervej 30  
StadtHorsens
Postleitzahl8700
Land, Gliederung (NUTS)Sydjylland (DK032)
LandDänemark
Zusätzliche InformationenOne (1) reactor to be delivered to: Station Molger Søndre Molgervej 30 8700 Horsens
5.1.2.
Erfüllungsort
PostanschriftTisetvej 74A  
StadtMårslet
Postleitzahl8320
Land, Gliederung (NUTS)Sydjylland (DK032)
LandDänemark
Zusätzliche InformationenOne (1) reactor to be delivered to: Station Ny Malling Tisetvej 74A 8320 Mårslet
5.1.2.
Erfüllungsort
PostanschriftElvej 6  
StadtTrige
Postleitzahl8380
Land, Gliederung (NUTS)Sydjylland (DK032)
LandDänemark
Zusätzliche InformationenTwo (2) reactors to be delivered to: Station Trige Elvej 6 8380 Trige
5.1.2.
Erfüllungsort
PostanschriftHønnerupvej 48  
StadtGelsted
Postleitzahl5591
Land, Gliederung (NUTS)Fyn (DK031)
LandDänemark
Zusätzliche InformationenOne (1) option for a reactor to be delivered to: Station Kingstrup Hønnerupvej 48 5591 Gelsted
5.1.3.
Geschätzte Dauer
Datum des Beginns19/02/2026
Enddatum der Laufzeit30/09/2030
5.1.6.
Allgemeine Informationen
Auftragsvergabeprojekt nicht aus EU-Mitteln finanziert
Die Beschaffung fällt unter das Übereinkommen über das öffentliche Beschaffungswesenja
5.1.10.
Zuschlagskriterien
Kriterium
ArtPreis
BezeichnungPrice
BeschreibungPrices must be stated in Appendix 3: Price List (Lot 1 doc. no. 24/10093-19, Lot2 doc. no. 24/10093-29 and Lot3 doc. no. 24/03003-39) and the defined price elements must be completed herein. Prices must be stated exclusive of VAT but inclusive of all other expenses associated with the purchase. Prices must be stated in EUR. When evaluating 'Price', the Contracting Authority will evaluate the total cost for each Lot individually, cf. the Appendix 3: Price lists (Lot 1 doc. no. 24/10093-19, Lot2 doc. no. 24/10093-29 and Lot3 doc. no. 24/10093-39). The evaluation of prices for each Lot is based on “Total price” in EUR from row 17&18 and column G in sheet “Total Eval price for each Lot Prices must be stated in EUR
Kategorie des Gewicht-ZuschlagskriteriumsGewichtung (Prozentanteil, genau)
Zuschlagskriterium — Zahl40
Kriterium
ArtQualität
BezeichnungTechnical solution
BeschreibungFor the evaluation of the sub-criteria the below should be enclosed: For each Lot the tenderer should include a technical solution description which - In detail describes the proposed solution (including design, components, processes, tools to be used etc.) and - Which demonstrates how and to which degree the competitive specifications as set out by the Contracting Authority, cf. the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093- 15 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26, are fulfilled, including any advantages elements. The tenderer should be thorough and precise when describing the technical solution, including technical advantages elements and level of fulfilment, as any insecurities and discrepancies may affect the evaluation negatively. Please note that all parts of the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093-16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26, concerning sound level, e.g. section 5.3.(sound enclosure), 11 and 13.3, will be evaluated as part of the sub-criteria “Sound level” and therefore will not be included in the evaluation of “Technical solution”. Further, please note that the elements marked in yellow in the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093- 16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26 are mandatory, cf. section 2.7.1 of the present Tender Conditions, and therefore are not included in the evaluation. In the evaluation of “Technical Solution”, the Contracting Authority will emphasize the following: The extent to which the detailed technical solution supports the delivery of high performing, well designed and robust reactors considering the scope and content of the assignment, cf. the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093-16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26. In this context, the elements listed below – and the fulfilment or lack thereof – are of particular importance: • General design - the overall technical solution for the shunt reactor design, including dimensions and accessibility. • Corrosion protection (cf. 5.5 Paint and surface treatment), including whether the protection level is higher or lower than C5vh and how all parts are treated. • Core type • Weight and Size, taking into consideration how this will affect the requirements for the foundations and stations • Tap changer (if applicable) and variation range (cf. 8. Tap Changer) • Oil type (physical characteristics such as sulphur) • Bushings (cf. 7. High-voltage connections and Bushings) • FAT- and SAT-procedure (cf. 6.5 Factory Acceptance Tests and Site Acceptance tests) The characteristics stated in the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093-16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26 are considered as an acceptable level of fulfilment. An overall evaluation will be made of this sub-criteria
Kategorie des Gewicht-ZuschlagskriteriumsGewichtung (Prozentanteil, genau)
Zuschlagskriterium — Zahl30
Kriterium
ArtQualität
BezeichnungSound level
BeschreibungThe evaluation will be based on a detailed and specific technical solution for the sound level, including: - Chosen methods, - Processes and tools for guaranteed sound power level. The evaluation of guaranteed sound level (cf. section 11. Sound Level in Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093-16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26is performed in 3 steps: Step 1): a. If the guaranteed sound power level is higher than the maximum value accepted the solution will be rejected as the minimum technical requirement is not fulfilled. b. If the guaranteed sound power level is equal to or lower than the maximum value accepted, the sound level is within an acceptable range - the score is preliminary set to a value of 5 (five), and the evaluation continues to step 2. Step 2): a. If NO external sound damping method is used to obtain the guaranteed value, the evaluation continues to step 3. b. If ANY external sound damping method is used to obtain the guaranteed value, the preliminary grade is reduced depending on the extent of the applied sound damping method: i. If Sound Panels (e.g., sandwich panels) are used, 3 (three) points will be deducted. ii. If Sound Screen is used, 3 (three) points will be deducted. iii. If Sound Housing is used, 5 (five) points will be deducted. (See note *) below for further description and definition of sound damping methods.) After the preliminary grade is reduced, the evaluation continues to step 3. Step 3): a. If sound power level is EQUAL TO the maximum value accepted by the Contracting Authority, the obtained preliminary score is the result of the evaluation. b. If sound power level is LOWER than the maximum value accepted by the Contracting Authority, the final score is obtained by adding 1 (one) point to the preliminary score for every dB the guaranteed sound power level is lower than the required maximum value. The final score cannot exceed the value 10 (ten), so no extra credit will be given for sound levels more than 10 dB lower than the maximum value. *) Note Definition of type of sound damping method (Step 2b i-iii). i. Sound Panels are panels attached directly to the tank wall, only partly covering one or more sides of the tank (e.g., sandwich panels). ii. Sound Screen is attached to the tank usually covering one or more complete sides. Typically, a screen is also installed with some centimetre distance between tank and screen, so valves, jacking points etc. must be accessed through hatches in the sound screen. iii. Sound Housing is an enclosure which surrounds the main tank, and it includes a roof. A sound house typically requires a separate or specially designed foundation.
Kategorie des Gewicht-ZuschlagskriteriumsGewichtung (Prozentanteil, genau)
Zuschlagskriterium — Zahl15
Kriterium
ArtQualität
BezeichnungContract Terms
BeschreibungFor the evaluation of the sub-criteria the tenderer is allowed to propose deviations to the elements of the contract identified as competitive elements in the contract terms: • Contract Agreement (doc. no. 24/10093-11, 24/10093- 21 and 24/10093-31), • Appendix 1: General Terms and Conditions for Purchase (doc. no. 24/10093-12), • Appendix 4 Time and Payment Schedule, (doc. no. 24/10093-20, 24/10093-30 and 24/10093-40) The deviations should be enclosed in the clarification list c.f. doc. no. 24/10093-10 and be included in the spreadsheet marked “Legal clarification”. The proposed deviations should be explicit and with explanation as to why they are made. Contract terms listed in section 2.7.1 are mandatory parts and deviations to these are not accepted. The tendered assignment must be performed on the basis of the attached contract terms. The tenderer is allowed to propose explicit and well-explained deviations to the listed competitive elements and the evaluation of “contract terms” will be based on the deviations. It should be noted that any deviation might impact the score as this is dependent on the content, clarity and consequence of the deviation. The following elements are considered competitive elements: • Appendix 1: General Terms and Conditions for Purchase and, where relevant, same Clauses and Sub-Clauses in the Contract Agreements: o Clause 2 (Requirements), except for Sub-Clause 2.3, 2.5 and 2.6 o Sub-clause 4.6 (Advance payment guarantee – except for what is stated as mandatory parts of the Tender Documents, cf. Sub-Section 2.7.1 above) o Clause 9 (Time of Delivery) o Clause 11 (Intellectual property rights) o Clause 12 (Late-delivery or non-delivery) o Clause 13 (Defects and remedies) o Clause 14 (Limitation of liability) o Clause 15 (Product liability) o Clause 16 (Insurance) o Clause 17 (Indemnification) o Clause 18 (Performance guarantee – except for what is stated as mandatory parts of the Tender Documents, cf. sub-section 2.7.1 above) o Sub-Clause 20.3 (HSE requirements) o Clause 25 (Termination) • Appendix 4: Time and Payment Schedules Deviations to these elements will be included in the evaluation and it is noted that any deviations may lead to a reduction of the score depending on the content, clarity, and consequence of the deviation. In this regard it is explicitly noted that deviations which are intended to limit liability and shift the financial risk in favor of the tenderer will be of particular importance in the evaluation. If the tenderer has no deviations to the contract terms, the maximum score of 10 will be awarded. An overall evaluation will be made of this sub-criterion. Please note that a minimum score of 4 must be achieved for the tender to be compliant, cf. sub-section 2.7.1.
Kategorie des Gewicht-ZuschlagskriteriumsGewichtung (Prozentanteil, genau)
Zuschlagskriterium — Zahl15
5.1.15.
Techniken
Rahmenvereinbarung
Keine Rahmenvereinbarung
Informationen über das dynamische Beschaffungssystem
Kein dynamisches Beschaffungssystem
5.1.16.
Weitere Informationen, Schlichtung und Nachprüfung
ÜberprüfungsstelleKlagenævnet for Udbud
Informationen über die Überprüfungsfristen: Complaints regarding a candidate not being pre-qualified must be filed with The Complaints Board for Public Procurement within 20 calendar days starting the day after the contracting authority has sent notification to the candidates involved, provided that the notification includes a short account of the relevant reasons for the decision. Other complaints must be filed with The Complaints Board for Public Procurement within: 1. 45 calendar days after the contracting authority has published a contract award notice in the Official Journal of the European Union (with effect from the day following the publication date); 2. 30 calendar days starting the day after the contracting authority has informed the tenderers in question, that the contracting authority has entered into a contract based on a framework agreement through reopening of competition or a dynamic purchasing system, provided that the notification includes a short account of the relevant reasons for the decision. 3. 6 months starting the day after the contracting authority has sent notification to the candidates/tenderers involved that the contracting authority has entered into the framework agreement, provided that the notification included a short account of the relevant reasons for the decision.
Organisation, die zusätzliche Informationen über das Vergabeverfahren bereitstelltEnerginet Eltransmission A/S
Organisation, die weitere Informationen für die Nachprüfungsverfahren bereitstelltKlagenævnet for Udbud
Organisation, aus deren Mitteln der Auftrag bezahlt wirdEnerginet Eltransmission A/S
Organisation, die die Zahlung ausführtEnerginet Eltransmission A/S
Organisation, die den Auftrag unterzeichnetEnerginet Eltransmission A/S
5.1.
LosLOT-0003
TitelLOT3 - NEA_ KAS-LAG
BeschreibungLot3: 6 units plus one (1) in option on 400kV, 70-140Mvar
Interne Kennung3-2
5.1.1.
Zweck
Art des AuftragsLieferleistungen
Haupteinstufung (cpv): 31000000 Elektrische Maschinen, Geräte, Ausstattung und Verbrauchsartikel; Beleuchtung
Zusätzliche Einstufung (cpv): 31170000 Transformatoren
Optionen
Beschreibung der OptionenThe Agreement contains options regarding one (1) additional variable shunt reactor that Supplier is obligated to deliver
5.1.2.
Erfüllungsort
PostanschriftGl. Ribevej 110  
StadtFredericia
Postleitzahl7000
Land, Gliederung (NUTS)Sydjylland (DK032)
LandDänemark
Zusätzliche InformationenFour (4) reactors to be delivered to: Station Ny Landerupgård Gl. Ribevej 110 7000 Fredericia
5.1.2.
Erfüllungsort
PostanschriftKassøvej 22  
StadtRødekro
Postleitzahl6230
Land, Gliederung (NUTS)Sydjylland (DK032)
LandDänemark
Zusätzliche InformationenTwo (2) reactors to be delivered to: Station Kassø Kassøvej 22 6230 Røde Kro
5.1.2.
Erfüllungsort
PostanschriftVandmøllevej 10  
StadtVejen
Postleitzahl6600
Land, Gliederung (NUTS)Sydjylland (DK032)
LandDänemark
Zusätzliche InformationenOne (1) reactor option to be delivered to: Station Revsing Vandmøllevej 10 6600 Vejen
5.1.3.
Geschätzte Dauer
Datum des Beginns23/02/2026
Enddatum der Laufzeit31/12/2030
5.1.6.
Allgemeine Informationen
Auftragsvergabeprojekt nicht aus EU-Mitteln finanziert
Die Beschaffung fällt unter das Übereinkommen über das öffentliche Beschaffungswesenja
5.1.10.
Zuschlagskriterien
Kriterium
ArtPreis
BezeichnungPrice
BeschreibungPrices must be stated in Appendix 3: Price List (Lot 1 doc. no. 24/10093-19, Lot2 doc. no. 24/10093-29 and Lot3 doc. no. 24/03003-39) and the defined price elements must be completed herein. Prices must be stated exclusive of VAT but inclusive of all other expenses associated with the purchase. Prices must be stated in EUR. When evaluating 'Price', the Contracting Authority will evaluate the total cost for each Lot individually, cf. the Appendix 3: Price lists (Lot 1 doc. no. 24/10093-19, Lot2 doc. no. 24/10093-29 and Lot3 doc. no. 24/10093-39). The evaluation of prices for each Lot is based on “Total price” in EUR from row 17&18 and column G in sheet “Total Eval price for each Lot Prices must be stated in EUR
Kategorie des Gewicht-ZuschlagskriteriumsGewichtung (Prozentanteil, genau)
Zuschlagskriterium — Zahl40
Kriterium
ArtQualität
BezeichnungTechnical solution
BeschreibungFor the evaluation of the sub-criteria the below should be enclosed: For each Lot the tenderer should include a technical solution description which - In detail describes the proposed solution (including design, components, processes, tools to be used etc.) and - Which demonstrates how and to which degree the competitive specifications as set out by the Contracting Authority, cf. the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093- 15 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26, are fulfilled, including any advantages elements. The tenderer should be thorough and precise when describing the technical solution, including technical advantages elements and level of fulfilment, as any insecurities and discrepancies may affect the evaluation negatively. Please note that all parts of the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093-16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26, concerning sound level, e.g. section 5.3.(sound enclosure), 11 and 13.3, will be evaluated as part of the sub-criteria “Sound level” and therefore will not be included in the evaluation of “Technical solution”. Further, please note that the elements marked in yellow in the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093- 16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26 are mandatory, cf. section 2.7.1 of the present Tender Conditions, and therefore are not included in the evaluation. In the evaluation of “Technical Solution”, the Contracting Authority will emphasize the following: The extent to which the detailed technical solution supports the delivery of high performing, well designed and robust reactors considering the scope and content of the assignment, cf. the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093-16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26. In this context, the elements listed below – and the fulfilment or lack thereof – are of particular importance: • General design - the overall technical solution for the shunt reactor design, including dimensions and accessibility. • Corrosion protection (cf. 5.5 Paint and surface treatment), including whether the protection level is higher or lower than C5vh and how all parts are treated. • Core type • Weight and Size, taking into consideration how this will affect the requirements for the foundations and stations • Tap changer (if applicable) and variation range (cf. 8. Tap Changer) • Oil type (physical characteristics such as sulphur) • Bushings (cf. 7. High-voltage connections and Bushings) • FAT- and SAT-procedure (cf. 6.5 Factory Acceptance Tests and Site Acceptance tests) The characteristics stated in the Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093-16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26 are considered as an acceptable level of fulfilment. An overall evaluation will be made of this sub-criteria
Kategorie des Gewicht-ZuschlagskriteriumsGewichtung (Prozentanteil, genau)
Zuschlagskriterium — Zahl30
Kriterium
ArtQualität
BezeichnungSound level
BeschreibungThe evaluation will be based on a detailed and specific technical solution for the sound level, including: - Chosen methods, - Processes and tools for guaranteed sound power level. The evaluation of guaranteed sound level (cf. section 11. Sound Level in Appendix 2A: Technical Specifications 63kA, doc. no. 24/10093-16 and Appendix 2A: Technical Specifications 80kA, doc. no. 24/10093-26is performed in 3 steps: Step 1): a. If the guaranteed sound power level is higher than the maximum value accepted the solution will be rejected as the minimum technical requirement is not fulfilled. b. If the guaranteed sound power level is equal to or lower than the maximum value accepted, the sound level is within an acceptable range - the score is preliminary set to a value of 5 (five), and the evaluation continues to step 2. Step 2): a. If NO external sound damping method is used to obtain the guaranteed value, the evaluation continues to step 3. b. If ANY external sound damping method is used to obtain the guaranteed value, the preliminary grade is reduced depending on the extent of the applied sound damping method: i. If Sound Panels (e.g., sandwich panels) are used, 3 (three) points will be deducted. ii. If Sound Screen is used, 3 (three) points will be deducted. iii. If Sound Housing is used, 5 (five) points will be deducted. (See note *) below for further description and definition of sound damping methods.) After the preliminary grade is reduced, the evaluation continues to step 3. Step 3): a. If sound power level is EQUAL TO the maximum value accepted by the Contracting Authority, the obtained preliminary score is the result of the evaluation. b. If sound power level is LOWER than the maximum value accepted by the Contracting Authority, the final score is obtained by adding 1 (one) point to the preliminary score for every dB the guaranteed sound power level is lower than the required maximum value. The final score cannot exceed the value 10 (ten), so no extra credit will be given for sound levels more than 10 dB lower than the maximum value. *) Note Definition of type of sound damping method (Step 2b i-iii). i. Sound Panels are panels attached directly to the tank wall, only partly covering one or more sides of the tank (e.g., sandwich panels). ii. Sound Screen is attached to the tank usually covering one or more complete sides. Typically, a screen is also installed with some centimetre distance between tank and screen, so valves, jacking points etc. must be accessed through hatches in the sound screen. iii. Sound Housing is an enclosure which surrounds the main tank, and it includes a roof. A sound house typically requires a separate or specially designed foundation.
Kategorie des Gewicht-ZuschlagskriteriumsGewichtung (Prozentanteil, genau)
Zuschlagskriterium — Zahl15
Kriterium
ArtQualität
BezeichnungContract Terms
BeschreibungFor the evaluation of the sub-criteria the tenderer is allowed to propose deviations to the elements of the contract identified as competitive elements in the contract terms: • Contract Agreement (doc. no. 24/10093-11, 24/10093- 21 and 24/10093-31), • Appendix 1: General Terms and Conditions for Purchase (doc. no. 24/10093-12), • Appendix 4 Time and Payment Schedule, (doc. no. 24/10093-20, 24/10093-30 and 24/10093-40) The deviations should be enclosed in the clarification list c.f. doc. no. 24/10093-10 and be included in the spreadsheet marked “Legal clarification”. The proposed deviations should be explicit and with explanation as to why they are made. Contract terms listed in section 2.7.1 are mandatory parts and deviations to these are not accepted. The tendered assignment must be performed on the basis of the attached contract terms. The tenderer is allowed to propose explicit and well-explained deviations to the listed competitive elements and the evaluation of “contract terms” will be based on the deviations. It should be noted that any deviation might impact the score as this is dependent on the content, clarity and consequence of the deviation. The following elements are considered competitive elements: • Appendix 1: General Terms and Conditions for Purchase and, where relevant, same Clauses and Sub-Clauses in the Contract Agreements: o Clause 2 (Requirements), except for Sub-Clause 2.3, 2.5 and 2.6 o Sub-clause 4.6 (Advance payment guarantee – except for what is stated as mandatory parts of the Tender Documents, cf. Sub-Section 2.7.1 above) o Clause 9 (Time of Delivery) o Clause 11 (Intellectual property rights) o Clause 12 (Late-delivery or non-delivery) o Clause 13 (Defects and remedies) o Clause 14 (Limitation of liability) o Clause 15 (Product liability) o Clause 16 (Insurance) o Clause 17 (Indemnification) o Clause 18 (Performance guarantee – except for what is stated as mandatory parts of the Tender Documents, cf. sub-section 2.7.1 above) o Sub-Clause 20.3 (HSE requirements) o Clause 25 (Termination) • Appendix 4: Time and Payment Schedules Deviations to these elements will be included in the evaluation and it is noted that any deviations may lead to a reduction of the score depending on the content, clarity, and consequence of the deviation. In this regard it is explicitly noted that deviations which are intended to limit liability and shift the financial risk in favor of the tenderer will be of particular importance in the evaluation. If the tenderer has no deviations to the contract terms, the maximum score of 10 will be awarded. An overall evaluation will be made of this sub-criterion. Please note that a minimum score of 4 must be achieved for the tender to be compliant, cf. sub-section 2.7.1.
Kategorie des Gewicht-ZuschlagskriteriumsGewichtung (Prozentanteil, genau)
Zuschlagskriterium — Zahl15
5.1.15.
Techniken
Rahmenvereinbarung
Keine Rahmenvereinbarung
Informationen über das dynamische Beschaffungssystem
Kein dynamisches Beschaffungssystem
5.1.16.
Weitere Informationen, Schlichtung und Nachprüfung
ÜberprüfungsstelleKlagenævnet for Udbud
Informationen über die Überprüfungsfristen: Complaints regarding a candidate not being pre-qualified must be filed with The Complaints Board for Public Procurement within 20 calendar days starting the day after the contracting authority has sent notification to the candidates involved, provided that the notification includes a short account of the relevant reasons for the decision. Other complaints must be filed with The Complaints Board for Public Procurement within: 1. 45 calendar days after the contracting authority has published a contract award notice in the Official Journal of the European Union (with effect from the day following the publication date); 2. 30 calendar days starting the day after the contracting authority has informed the tenderers in question, that the contracting authority has entered into a contract based on a framework agreement through reopening of competition or a dynamic purchasing system, provided that the notification includes a short account of the relevant reasons for the decision. 3. 6 months starting the day after the contracting authority has sent notification to the candidates/tenderers involved that the contracting authority has entered into the framework agreement, provided that the notification included a short account of the relevant reasons for the decision.
Organisation, die zusätzliche Informationen über das Vergabeverfahren bereitstelltEnerginet Eltransmission A/S
Organisation, die weitere Informationen für die Nachprüfungsverfahren bereitstelltKonkurrence- og Forbrugerstyrelsen
Organisation, aus deren Mitteln der Auftrag bezahlt wirdEnerginet Eltransmission A/S
Organisation, die die Zahlung ausführtEnerginet Eltransmission A/S
Organisation, die den Auftrag unterzeichnetEnerginet Eltransmission A/S
6. Ergebnisse
Wert aller in dieser Bekanntmachung vergebenen Verträge108 467 678,00 EUR
6.1.
Ergebnis, Los-– KennungLOT-0001
Status der PreisträgerauswahlEs wurde mindestens ein Gewinner ermittelt.
6.1.2.
Informationen über die Gewinner
Wettbewerbsgewinner
Offizielle BezeichnungGrid Solutions DENMARK, BRANCH OF Grid Solutions SAS Frankrig
Angebot
Kennung des AngebotsLOT1 - SLF02 - Grid Solutions DENMARK, BRANCH OF Grid Solutions SAS Frankrig
Kennung des Loses oder der Gruppe von LosenLOT-0001
Wert des Angebots31 455 395,00 EUR
Das Angebot wurde in die Rangfolge eingeordnetnein
Bei dem Angebot handelt es sich um eine Variantenein
Vergabe von UnteraufträgenNein
Informationen zum Auftrag
Kennung des AuftragsLOT1 - SLF02 - Grid Solutions DENMARK, BRANCH OF Grid Solutions SAS Frankrig
Datum des Vertragsabschlusses23/02/2026
Organisation, die den Auftrag unterzeichnetEnerginet Eltransmission A/S
6.1.4.
Statistische Informationen
Eingegangene Angebote oder Teilnahmeanträge
Art der eingegangenen EinreichungenAngebote
Anzahl der eingegangenen Angebote oder Teilnahmeanträge3
Bandbreite der Angebote
Wert des niedrigsten zulässigen Angebots31 455 395,00 EUR
Wert des höchsten zulässigen Angebots43 918 542,00 EUR
6.1.
Ergebnis, Los-– KennungLOT-0002
Status der PreisträgerauswahlEs wurde mindestens ein Gewinner ermittelt.
6.1.2.
Informationen über die Gewinner
Wettbewerbsgewinner
Offizielle BezeichnungHitachi Energy Denmark A/S
Angebot
Kennung des AngebotsLOT2 - NEA_ MOL, MAL, TRI - Hitachi Energy Denmark A/S
Kennung des Loses oder der Gruppe von LosenLOT-0002
Wert des Angebots33 587 230,00 EUR
Das Angebot wurde in die Rangfolge eingeordnetnein
Bei dem Angebot handelt es sich um eine Variantenein
Vergabe von UnteraufträgenNein
Informationen zum Auftrag
Kennung des AuftragsLOT2 - NEA_ MOL, MAL, TRI - Hitachi Energy Denmark A/S
Datum des Vertragsabschlusses19/02/2026
Organisation, die den Auftrag unterzeichnetEnerginet Eltransmission A/S
6.1.4.
Statistische Informationen
Eingegangene Angebote oder Teilnahmeanträge
Art der eingegangenen EinreichungenAngebote
Anzahl der eingegangenen Angebote oder Teilnahmeanträge3
Bandbreite der Angebote
Wert des niedrigsten zulässigen Angebots32 330 395,00 EUR
Wert des höchsten zulässigen Angebots41 318 748,00 EUR
6.1.
Ergebnis, Los-– KennungLOT-0003
Status der PreisträgerauswahlEs wurde mindestens ein Gewinner ermittelt.
6.1.2.
Informationen über die Gewinner
Wettbewerbsgewinner
Offizielle BezeichnungGrid Solutions DENMARK, BRANCH OF Grid Solutions SAS Frankrig
Angebot
Kennung des AngebotsLOT3 - NEA_ KAS-LAG - Grid Solutions DENMARK, BRANCH OF Grid Solutions SAS Frankrig
Kennung des Loses oder der Gruppe von LosenLOT-0003
Wert des Angebots43 425 053,00 EUR
Das Angebot wurde in die Rangfolge eingeordnetnein
Bei dem Angebot handelt es sich um eine Variantenein
Vergabe von UnteraufträgenNein
Informationen zum Auftrag
Kennung des AuftragsLOT3 - NEA_ KAS-LAG - Grid Solutions DENMARK, BRANCH OF Grid Solutions SAS Frankrig
Datum des Vertragsabschlusses23/02/2026
Organisation, die den Auftrag unterzeichnetEnerginet Eltransmission A/S
6.1.4.
Statistische Informationen
Eingegangene Angebote oder Teilnahmeanträge
Art der eingegangenen EinreichungenAngebote
Anzahl der eingegangenen Angebote oder Teilnahmeanträge3
Bandbreite der Angebote
Wert des niedrigsten zulässigen Angebots43 425 053,00 EUR
Wert des höchsten zulässigen Angebots61 529 431,00 EUR
8. Organisationen
8.1.
ORG-0001
Offizielle BezeichnungEnerginet Eltransmission A/S
Registrierungsnummer39314878
PostanschriftTonne Kjærsvej 65
StadtFredericia
Postleitzahl7000
Land, Gliederung (NUTS)Sydjylland (DK032)
LandDänemark
KontaktpersonProcurement - B
E-Mailprocurement@energinet.dk
Telefon+45 70102244
Internetadressehttps://eu.eu-supply.com/ctm/supplier/publictenders?B=ENERGINET
Profil des Erwerbershttps://eu.eu-supply.com/ctm/company/companyinformation/index/228008
Rollen dieser Organisation
Beschaffer
Organisation, die zusätzliche Informationen über das Vergabeverfahren bereitstellt
Organisation, die den Auftrag unterzeichnet
Organisation, aus deren Mitteln der Auftrag bezahlt wird
Organisation, die die Zahlung ausführt
8.1.
ORG-0002
Offizielle BezeichnungGrid Solutions DENMARK, BRANCH OF Grid Solutions SAS Frankrig
Größe des WirtschaftsteilnehmersGroßunternehmen
RegistrierungsnummerDK27550835
PostanschriftJupitervej 6
StadtKolding
Postleitzahl6000
Land, Gliederung (NUTS)Sydjylland (DK032)
LandDänemark
E-Mailole.nielsen@ge.com
Telefon+45 76201180
Rollen dieser Organisation
Bieter
Gewinner dieser LoseLOT-0001, LOT-0003
8.1.
ORG-0003
Offizielle BezeichnungHitachi Energy Denmark A/S
Größe des WirtschaftsteilnehmersGroßunternehmen
Registrierungsnummer39856638
PostanschriftMeterbuen 33
StadtSkovlunde
Postleitzahl2740
Land, Gliederung (NUTS)Københavns omegn (DK012)
LandDänemark
E-Mailper.nissen@hitachienergy.com
Telefon+45 20117919
Rollen dieser Organisation
Bieter
Gewinner dieser LoseLOT-0002
8.1.
ORG-0004
Offizielle BezeichnungKlagenævnet for Udbud
Registrierungsnummer37795526
PostanschriftNævnenes Hus, Toldboden 2
StadtViborg
Postleitzahl8800
Land, Gliederung (NUTS)Vestjylland (DK041)
LandDänemark
E-Mailklfu@naevneneshus.dk
Telefon+45 72405708
Internetadressehttps://naevneneshus.dk/start-din-klage/klagenaevnet-for-udbud/
Rollen dieser Organisation
Überprüfungsstelle
Organisation, die weitere Informationen für die Nachprüfungsverfahren bereitstellt
8.1.
ORG-0005
Offizielle BezeichnungKonkurrence- og Forbrugerstyrelsen
Registrierungsnummer10294819
PostanschriftCarl Jacobsen Vej 35
StadtValby
Postleitzahl2500
Land, Gliederung (NUTS)Byen København (DK011)
LandDänemark
E-Mailkfst@kfst.dk
Telefon+45 41715000
Internetadressehttp://www.kfst.dk
Rollen dieser Organisation
Organisation, die weitere Informationen für die Nachprüfungsverfahren bereitstellt
8.1.
ORG-0006
Offizielle BezeichnungMercell Holding ASA
Registrierungsnummer980921565
PostanschriftAskekroken 11
StadtOslo
Postleitzahl0277
Land, Gliederung (NUTS)Oslo (NO081)
LandNorwegen
KontaktpersoneSender
E-Mailpublication@mercell.com
Telefon+47 21018800
Fax+47 21018801
Internetadressehttp://mercell.com/
Rollen dieser Organisation
TED eSender
Informationen zur Bekanntmachung
Kennung/Fassung der Bekanntmachung0a4313a0-e4ae-4481-a81f-68c63c856062  -  01
FormulartypErgebnis
Art der BekanntmachungBekanntmachung vergebener Aufträge oder Zuschlagsbekanntmachung – Standardregelung
Unterart der Bekanntmachung30
Datum der Übermittlung der Bekanntmachung11/03/2026 09:31:24 (UTC+00:00) Westeuropäische Zeit, GMT
Bekanntmachung — eSender-Übermittlungsdatum11/03/2026 09:31:24 (UTC+00:00) Westeuropäische Zeit, GMT
Sprachen, in denen diese Bekanntmachung offiziell verfügbar istEnglisch
Veröffentlichungsnummer der Bekanntmachung172984-2026
ABl. S – Nummer der Ausgabe50/2026
Datum der Veröffentlichung12/03/2026