Zusätzliche Angaben
1) The EU cable qualification system by Vattenfall published in the e-Vergabe;
2) Participation contact the e-Vergabe and load up a letter of interest;
3) The questionnaire is sent to supplier by Vattenfall from e-Vergabe;
4) Factory/supplier fills in the questionnaires and resends to Vattenfall according to instruction from e-Vergabe;
5) Vattenfall evaluates the answers in the submitted questionnaires;
6) If Vattenfall approves the answers on questionnaires, Vattenfall could request an on-site factory audit to verify answers to questionnaires and capability to meet technical requirements as set forth in the technical specifications;
7) For supply to Vattenfall Sweden the prequalified suppliers also need to be registered and approved in a IT-system;
8) Based on Vattenfall approved final audit report, factory/supplier is awarded PQ status;
9) If factory/supplier is located in ‘risk country’, also Vattenfall approved on-site CSR audit is necessary for PQ status.
(use link eVergabe).