Beschreibung der Beschaffung
Supporting Partners (SPs), consisting primarily of donors, lenders, and implementing agencies, have responded to the impending collapse of the wastewater sector as outlined in two key documents, which were coordinated with and endorsed by the Ministry of Energy and Water (MoEW).
The first of these documents is the "Roadmap to Recovery of the Water Sector in Lebanon", which has a 5-year planning horizon and aims to bridge between emergency measures needed to maintain services and longer-term reform.
The second document is UNICEF"s "Wastewater Treatment 2 years Support Concept Model" for supporting wastewater management by water establishments (WEs) during the handover from the CDR to the four regional WE. Preparations are underway across several Supporting Partners to contribute to the response, e.g. financing the rehabilitation, operation, and maintenance of selected wastewater treatment plants (WWTP) for two years as well as contracting Supervisory Consulting Firms to take part of the supervision and monitoring of the private operators (POs). UNICEF plans to additionally second an Electro-Mechanical Engineer to each water establishment, as well as incentivize select WE engineers who will shadow them and the "seconded" Process Engineers provided by the Technical Assistance Contractor (TAC) (see below).
Through this tender, the Technical Assistance Contractor (TAC), i.e. the winning bidder, will be providing four process engineers for specified monitoring and supervision activities of the private operators contracted by SPs. Each of the four process engineers will be based at one of the four regional water establishment for a preliminary period of 22 months and will collaborate with all relevant stakeholders such as internal and seconded WE personnel, Municipalities, the Ministry of Energy and Water, Supporting Partners, Supervisory Consulting Firm (SCF) and the contracted private operators.
The TAC will hold the contracts of all Process Engineers and additional experts solicited to support their mission and the delivery of three work packages with their respective milestones across all 4 WEs:
Work Package 1: Supervise Operations of Up to 30 WWTPs
The TAC will provide technical expertise and direction in the water establishments monitoring and supervision of the private operators of the wastewater treatment plants in their daily and routine operation and maintenance works, through the Process Engineers, and against contractual performance indicators.
Work Package 2: Develop Resident Capacity on WWTP Processes and Supervision
The TAC will ensure WE staff are able to supervise WWTP operations and POs within the framework of performance-based contracts and assume their mandate by the end of the contract period. Training/coaching is expected from POs, SCFs, and SPs, and the TAC must ensure supply and demand for skill development are well matched and provide supplementary training/coaching to raise WEs" capacity to the level required.
Work package 3: Revise Performance-Based WWTP Private Operator Contracts
The TAC will use evidence/data generated throughout the implementation period to critically evaluate the success of Performance-Based Contracts and suggest modifications to future contracts. They will further analyse the true cost of operation, maintenance, and associated services in detail to inform future tariffing scenarios.