<?xml version="1.0" encoding="UTF-8" standalone="no"?><ContractAwardNotice xmlns="urn:oasis:names:specification:ubl:schema:xsd:ContractAwardNotice-2" xmlns:cac="urn:oasis:names:specification:ubl:schema:xsd:CommonAggregateComponents-2" xmlns:cbc="urn:oasis:names:specification:ubl:schema:xsd:CommonBasicComponents-2" xmlns:ccts-cct="urn:un:unece:uncefact:data:specification:CoreComponentTypeSchemaModule:2" xmlns:efac="http://data.europa.eu/p27/eforms-ubl-extension-aggregate-components/1" xmlns:efbc="http://data.europa.eu/p27/eforms-ubl-extension-basic-components/1" xmlns:efext="http://data.europa.eu/p27/eforms-ubl-extensions/1" xmlns:ext="urn:oasis:names:specification:ubl:schema:xsd:CommonExtensionComponents-2" xmlns:qdt="urn:oasis:names:specification:ubl:schema:xsd:QualifiedDataTypes-2" xmlns:udt="urn:oasis:names:specification:bdndr:schema:xsd:UnqualifiedDataTypes-1"><ext:UBLExtensions><ext:UBLExtension><ext:ExtensionContent><efext:EformsExtension><efac:ContractModification><!--BT-1501(n)-Contract (Order: 01)--><efbc:ChangedNoticeIdentifier>9877d7ba-8081-4184-864a-e5d75990eb04-01</efbc:ChangedNoticeIdentifier><!--BT-1501(c)-Contract (Order: 02)--><efbc:ModifiedContractIdentifier schemeName="contract">CON-0001</efbc:ModifiedContractIdentifier><efac:Change><!--BT-202-Contract (Order: 01)--><efbc:ChangeDescription languageID="DEU">MKA005 Bei der Herstellung der Signalgründungen und der Gleisquerungen wurde während der Bauarbeiten vor Ort eine Bodenklasse 6-7 festgestellt. Diese weicht im Wesentlichen von der im Bodengutachten und der im Hauptleistungsverzeichnis enthaltenen Bodenklasse 3-5 ab. Um die ausgeschriebenen Tiefbauleistungen ausführen zu können sind zusätzliche vorbereitende Leistungen wie Auflockerungsbohrungen und Felsfräsungen notwendig
MKA014 Im Rahmen der Errichtung von Gleisquerungen, Schacht- und Muffenstandorten sowie ähnlichen baulichen Maßnahmen ist der
anstehende Boden im Gleisbereich nicht für eine erneute Verwendung geeignet. Aus diesem Grund muss dieser Boden durch
KG2-Material ersetzt werden.

MKA016 Bei der Herstellung des Längstrassenaushubs wurde während der Bauarbeiten vor Ort eine Bodenklasse 6–7 festgestellt. Diese weicht wesentlich von der im Bodengutachten sowie im Hauptleistungsverzeichnis angegebenen Bodenklasse 3–5 ab. Um das ausgeschriebene Kabelführungssystem fachgerecht herstellen zu können, muss der Bodenaushub teilweise unter Einsatz einer Felsfräse und eines Anbaumeißels erfolgen – Leistungen, die im Hauptleistungsverzeichnis nicht enthalten sind.

MKA019 Im Rahmen der neu zu bauenden Betonkabelkanäle und Schächte wurde festgestellt, dass sich in den Aushubbereichen teilweise
alte Fundamente befinden. Diese müssen abgebrochen und abtransportiert werden, um den Neubau zu ermöglichen.

MKA020 Um ein durchgängiges Kabelführungssystem zu gewährleisten, ist es notwendig, an den Bahnübergängen bei Bahn-km 132,500,
136,700 und 138,900 Straßenquerungen herzustellen. Da Tiefbauleistungen Teil der Beauftragung sind, werden diese Arbeiten
fortlaufend durchgeführt. Die Herstellung von Straßenquerungen an den Bahnübergängen ist jedoch nicht Bestandteil des
Hauptvertrages und wird daher als zusätzliche Leistung angezeigt.

MKA024 Zum Herstellen einer durchgängigen Kabelführung ist es erforderlich, in bestehenden und neu zu errichtenden Betonkabelkanälen
sowie in Kabelschächten Ausschnitte herzustellen. Diese Ausschnitte dienen dazu, die LST-Komponenten, wie beispielsweise
Achszähler, Signale und weitere sicherheitsrelevante Einrichtungen, anschließen zu können. Da Tiefbauleistungen Teil der
Beauftragung sind, werden diese Arbeiten fortlaufend durchgeführt. Die Herstellung von Ausschnitten an den Betonkabelkanälen
sowie in Kabelschächten ist jedoch nicht Bestandteil des Hauptvertrags und wird daher als zusätzliche Leistung angezeigt.
</efbc:ChangeDescription></efac:Change><efac:ChangeReason><!--BT-200-Contract (Order: 01)--><cbc:ReasonCode listName="modification-justification">add-wss</cbc:ReasonCode><!--BT-201-Contract (Order: 02)--><efbc:ReasonDescription languageID="DEU">MKA005 Die Abweichung wurde während der Bauarbeiten vor Ort festgestellt. Es handelt sich nicht um eine gesonderte Leistung, sondern um eine technisch notwendige vorbereitende Maßnahme, um die vertraglich geschuldete Leistung (Rammrohrgründung und Kabelschächte) überhaupt erbringen zu können. Der AN ist verpflichtet, alle Maßnahmen zu ergreifen, die zur ordnungsgemäßen Ausführung seiner Leistung erforderlich sind. Es entstehen zusätzliche Kosten durch eine doppelte Baustelleneinrichtung (BE-Flächen, Baubüro, Verwaltungsbereiche, sanitäre Einrichtungen, etc.). Zusätzlich müssten geeignete Flächen gefunden und reserviert werden. Bei der Aufteilung der Aufgaben zwischen unterschiedlichen Auftragnehmern könnten die Verantwortlichkeiten und Haftungsfragen im Falle von Fehlern schwer nachvollziehbar und klärbar sein.

MKA014 Die Maßnahme wird unmittelbar nach den baulichen Maßnahmen, der Errichtung von Gleisquerungen, Schacht- und
Muffenstandorten sowie ähnlichen baulichen Maßnahmen, ausgeführt, sodass die Prozesse zur gleichen Zeit stattfinden. Ein
Wechsel des Bauunternehmers würde nicht nur Verzögerungen bei den Bauarbeiten nach sich ziehen, sondern auch zu
möglichen Problemen bei der Koordination der bereits begonnenen Teilmaßnahmen führen.
Es entstehen zusätzliche Kosten durch eine doppelte Baustelleneinrichtung (BE-Flächen, Baubüro, Verwaltungsbereiche,
sanitäre Einrichtungen, etc.). Zusätzlich müssten geeignete Flächen gefunden und reserviert werden. Bei der Aufteilung der
Aufgaben zwischen unterschiedlichen Auftragnehmern könnten die Verantwortlichkeiten und Haftungsfragen im Falle von
Fehlern schwer nachvollziehbar und klärbar sein.

MKA016 Ein Wechsel des Auftragnehmers für die Erstellung des Aushubs ist aus technischen Gründen nicht möglich. Der derzeit beauftragte Unternehmer verfügt über die erforderliche Spezialtechnik und das notwendige Know-how zur fachgerechten Ausführung der Arbeiten unter den vorgefundenen Bodenverhältnissen. Ein Wechsel würde den Bauablauf erheblich stören, zu Verzögerungen führen und zusätzliche Kosten verursachen. Darüber hinaus bestehen vergaberechtliche und haftungsrechtliche Risiken, die einen Wechsel ausschließen. 

MKA019 Die Maßnahme wird unmittelbar während der baulichen Maßnahmen, der Errichtung der neuen Betonkabelkanäle und
Schächte, ausgeführt, sodass die Prozesse zur gleichen Zeit stattfinden. Ein Wechsel des Bauunternehmers würde nicht nur
Verzögerungen bei den Bauarbeiten nach sich ziehen, sondern auch zu möglichen Problemen bei der Koordination der bereits
begonnenen Teilmaßnahmen führen.
Es entstehen zusätzliche Kosten durch eine doppelte Baustelleneinrichtung (BE-Flächen, Baubüro, Verwaltungsbereiche,
sanitäre Einrichtungen, etc.). Zusätzlich müssten geeignete Flächen gefunden und reserviert werden. Bei der Aufteilung der
Aufgaben zwischen unterschiedlichen Auftragnehmern könnten die Verantwortlichkeiten und Haftungsfragen im Falle von
Fehlern schwer nachvollziehbar und klärbar sein.

MKA020 Die Maßnahme wird unmittelbar im Rahmen der baulichen Arbeiten zur Herstellung des neuen Kabelführungssystems
ausgeführt. Das Kabelführungssystem wird in fortlaufender Bauweise entlang eines Strangs hergestellt und um diese
fortlaufende Bauweise nicht zu unterbrechen, sind die Straßenquerungen notwendig. Ein Wechsel des Bauunternehmers
würde nicht nur zu Verzögerungen bei den Bauarbeiten führen, sondern auch mögliche Probleme bei der Koordination der
bereits begonnenen Teilmaßnahmen verursachen.
Es entstehen zusätzliche Kosten durch eine doppelte Baustelleneinrichtung (BE-Flächen, Baubüro, Verwaltungsbereiche,
sanitäre Einrichtungen, etc.). Zusätzlich müssten geeignete Flächen gefunden und reserviert werden. Bei der Aufteilung der
Aufgaben zwischen unterschiedlichen Auftragnehmern könnten die Verantwortlichkeiten und Haftungsfragen im Falle von
Fehlern schwer nachvollziehbar und klärbar sein.

MKA024 Die Maßnahme wird im Rahmen der baulichen Arbeiten zur Herstellung des neuen Kabelführungssystems ausgeführt. Das
Kabelführungssystem entsteht in fortlaufender Bauweise entlang eines Strangs. Um diese fortlaufende Bauweise nicht zu
unterbrechen, ist die Herstellung von Ausschnitten an den Betonkabelkanälen sowie in Kabelschächten zeitgleich mit den
Arbeiten notwendig. Ein Wechsel des Bauunternehmens würde nicht nur zu Verzögerungen im Bauablauf führen, sondern
auch potenzielle Probleme bei der Koordination der bereits begonnenen Teilmaßnahmen verursachen.
Es entstehen zusätzliche Kosten durch eine doppelte Baustelleneinrichtung (BE-Flächen, Baubüro, Verwaltungsbereiche,
sanitäre Einrichtungen, etc.). Zusätzlich müssten geeignete Flächen gefunden und reserviert werden. Bei der Aufteilung der
Aufgaben zwischen unterschiedlichen Auftragnehmern könnten die Verantwortlichkeiten und Haftungsfragen im Falle von
Fehlern schwer nachvollziehbar und klärbar sein.
</efbc:ReasonDescription></efac:ChangeReason></efac:ContractModification><efac:NoticeResult><efac:LotResult><!--OPT-322-LotResult (Order: 02)--><cbc:ID>RES-0001</cbc:ID><efac:LotTender><!--OPT-320-LotResult (Order: 02)--><cbc:ID schemeName="tender">TEN-0001</cbc:ID></efac:LotTender><efac:SettledContract><!--OPT-315-LotResult (Order: 01)--><cbc:ID schemeName="contract">CON-0001</cbc:ID></efac:SettledContract><efac:TenderLot><!--BT-13713-LotResult (Order: 01)--><cbc:ID schemeName="Lot">LOT-0001</cbc:ID></efac:TenderLot></efac:LotResult><efac:LotTender><!--OPT-321-Tender (Order: 02)--><cbc:ID>TEN-0001</cbc:ID><efac:TenderingParty><!--OPT-310-Tender (Order: 01)--><cbc:ID schemeName="tendering-party">TPA-0001</cbc:ID></efac:TenderingParty><efac:TenderLot><!--BT-13714-Tender (Order: 01)--><cbc:ID schemeName="Lot">LOT-0001</cbc:ID></efac:TenderLot><efac:TenderReference><!--BT-3201-Tender (Order: 01)--><cbc:ID>2024948536</cbc:ID></efac:TenderReference></efac:LotTender><efac:SettledContract><!--OPT-316-Contract (Order: 01)--><cbc:ID>CON-0001</cbc:ID><!--BT-1451-Contract (Order: 02)--><cbc:AwardDate>2024-04-11+02:00</cbc:AwardDate><!--BT-145-Contract (Order: 03)--><cbc:IssueDate>2024-04-22+02:00</cbc:IssueDate><efac:ContractReference><!--BT-150-Contract (Order: 01)--><cbc:ID>CON-0001 - Bahnbau Weidlich GmbH</cbc:ID></efac:ContractReference><efac:LotTender><!--BT-3202-Contract (Order: 02)--><cbc:ID schemeName="tender">TEN-0001</cbc:ID></efac:LotTender></efac:SettledContract><efac:TenderingParty><!--OPT-210-Tenderer (Order: 01)--><cbc:ID>TPA-0001</cbc:ID><efac:Tenderer><!--OPT-300-Tenderer (Order: 01)--><cbc:ID schemeName="organization">ORG-0003</cbc:ID></efac:Tenderer></efac:TenderingParty></efac:NoticeResult><efac:NoticeSubType><!--OPP-070-notice (Order: 01)--><cbc:SubTypeCode listName="notice-subtype">39</cbc:SubTypeCode></efac:NoticeSubType><efac:Organizations><efac:Organization><efac:Company><!--BT-505-Organization-Company (Order: 01)--><cbc:WebsiteURI>http://www.deutschebahn.com/bieterportal/</cbc:WebsiteURI><cac:PartyIdentification><!--OPT-200-Organization-Company (Order: 02)--><cbc:ID>ORG-0001</cbc:ID></cac:PartyIdentification><cac:PartyName><!--BT-500-Organization-Company (Order: 02)--><cbc:Name languageID="DEU">DB InfraGO AG – Geschäftsbereich Fahrweg (Bukr 16)</cbc:Name></cac:PartyName><cac:PostalAddress><!--BT-510(a)-Organization-Company (Order: 08)--><cbc:StreetName>Adam-Riese-Straße 11-13</cbc:StreetName><!--BT-513-Organization-Company (Order: 20)--><cbc:CityName>Frankfurt Main</cbc:CityName><!--BT-512-Organization-Company (Order: 21)--><cbc:PostalZone>60327</cbc:PostalZone><!--BT-507-Organization-Company (Order: 23)--><cbc:CountrySubentityCode listName="nuts">DE712</cbc:CountrySubentityCode><cac:Country><!--BT-514-Organization-Company (Order: 02)--><cbc:IdentificationCode listName="country">DEU</cbc:IdentificationCode></cac:Country></cac:PostalAddress><cac:PartyLegalEntity><!--BT-501-Organization-Company (Order: 03)--><cbc:CompanyID>fb197f94-7578-4673-8a57-4642ae120532</cbc:CompanyID></cac:PartyLegalEntity><cac:Contact><!--BT-502-Organization-Company (Order: 03)--><cbc:Name>FE.EI-S-E</cbc:Name><!--BT-503-Organization-Company (Order: 06)--><cbc:Telephone>+49 89130872535</cbc:Telephone><!--BT-506-Organization-Company (Order: 08)--><cbc:ElectronicMail>Nora.Nura@deutschebahn.com</cbc:ElectronicMail></cac:Contact></efac:Company></efac:Organization><efac:Organization><efac:Company><cac:PartyIdentification><!--OPT-200-Organization-Company (Order: 02)--><cbc:ID>ORG-0002</cbc:ID></cac:PartyIdentification><cac:PartyName><!--BT-500-Organization-Company (Order: 02)--><cbc:Name languageID="DEU">Vergabekammer des Bundes</cbc:Name></cac:PartyName><cac:PostalAddress><!--BT-510(a)-Organization-Company (Order: 08)--><cbc:StreetName>Kaiser-Friedrich-Straße 16</cbc:StreetName><!--BT-513-Organization-Company (Order: 20)--><cbc:CityName>Bonn</cbc:CityName><!--BT-512-Organization-Company (Order: 21)--><cbc:PostalZone>53113</cbc:PostalZone><!--BT-507-Organization-Company (Order: 23)--><cbc:CountrySubentityCode listName="nuts">DEA22</cbc:CountrySubentityCode><cac:Country><!--BT-514-Organization-Company (Order: 02)--><cbc:IdentificationCode listName="country">DEU</cbc:IdentificationCode></cac:Country></cac:PostalAddress><cac:PartyLegalEntity><!--BT-501-Organization-Company (Order: 03)--><cbc:CompanyID>0a9ea480-08e4-4ab6-bf12-d722d0ad54b6</cbc:CompanyID></cac:PartyLegalEntity><cac:Contact><!--BT-503-Organization-Company (Order: 06)--><cbc:Telephone>+49 22894990</cbc:Telephone><!--BT-506-Organization-Company (Order: 08)--><cbc:ElectronicMail>vk@bundeskartellamt.bund.de</cbc:ElectronicMail></cac:Contact></efac:Company></efac:Organization><efac:Organization><efac:Company><cac:PartyIdentification><!--OPT-200-Organization-Company (Order: 02)--><cbc:ID>ORG-0003</cbc:ID></cac:PartyIdentification><cac:PartyName><!--BT-500-Organization-Company (Order: 02)--><cbc:Name languageID="DEU">Bahnbau Weidlich GmbH</cbc:Name></cac:PartyName><cac:PostalAddress><!--BT-510(a)-Organization-Company (Order: 08)--><cbc:StreetName>Gewerbering 22</cbc:StreetName><!--BT-513-Organization-Company (Order: 20)--><cbc:CityName>Heinersdorfergrund</cbc:CityName><!--BT-512-Organization-Company (Order: 21)--><cbc:PostalZone>08468</cbc:PostalZone><!--BT-507-Organization-Company (Order: 23)--><cbc:CountrySubentityCode listName="nuts">DED44</cbc:CountrySubentityCode><cac:Country><!--BT-514-Organization-Company (Order: 02)--><cbc:IdentificationCode listName="country">DEU</cbc:IdentificationCode></cac:Country></cac:PostalAddress><cac:PartyLegalEntity><!--BT-501-Organization-Company (Order: 03)--><cbc:CompanyID>5ab9b1f1-89e1-4015-9fe8-cfe98eceda99</cbc:CompanyID></cac:PartyLegalEntity><cac:Contact><!--BT-503-Organization-Company (Order: 06)--><cbc:Telephone>+49</cbc:Telephone><!--BT-506-Organization-Company (Order: 08)--><cbc:ElectronicMail>bieterportal-alt@deutschebahn.com</cbc:ElectronicMail></cac:Contact></efac:Company></efac:Organization><efac:Organization><efac:Company><cac:PartyIdentification><cbc:ID schemeName="organization">ORG-0004</cbc:ID></cac:PartyIdentification><cac:PartyName><cbc:Name languageID="DEU">Datenservice Öffentlicher Einkauf (in Verantwortung des Beschaffungsamts des BMI)</cbc:Name></cac:PartyName><cac:PostalAddress><cbc:CityName>Bonn</cbc:CityName><cbc:PostalZone>53119</cbc:PostalZone><cbc:CountrySubentityCode listName="nuts">DEA22</cbc:CountrySubentityCode><cac:Country><cbc:IdentificationCode listName="country">DEU</cbc:IdentificationCode></cac:Country></cac:PostalAddress><cac:PartyLegalEntity><cbc:CompanyID schemeID="002">0204:994-DOEVD-83</cbc:CompanyID></cac:PartyLegalEntity><cac:Contact><cbc:Telephone>+49228996100</cbc:Telephone><cbc:ElectronicMail>noreply.esender_hub@bescha.bund.de</cbc:ElectronicMail></cac:Contact></efac:Company></efac:Organization></efac:Organizations><efac:Publication><efbc:NoticePublicationID schemeName="ojs-notice-id">00511865-2025</efbc:NoticePublicationID><efbc:GazetteID schemeName="ojs-id">148/2025</efbc:GazetteID><efbc:PublicationDate>2025-08-05+02:00</efbc:PublicationDate></efac:Publication></efext:EformsExtension></ext:ExtensionContent></ext:UBLExtension></ext:UBLExtensions><!--OPT-001-notice (Order: 02)--><cbc:UBLVersionID>2.3</cbc:UBLVersionID><!--OPT-002-notice (Order: 03)--><cbc:CustomizationID>eforms-sdk-1.13</cbc:CustomizationID><!--BT-701-notice (Order: 06)--><cbc:ID schemeName="notice-id">bda7fe67-35df-4729-91f0-7f2420ce155e</cbc:ID><!--BT-04-notice (Order: 09)--><cbc:ContractFolderID>f6896454-b537-44e4-8b38-082a3acd4368</cbc:ContractFolderID><!--BT-05(a)-notice (Order: 10)--><cbc:IssueDate>2025-08-04+02:00</cbc:IssueDate><!--BT-05(b)-notice (Order: 11)--><cbc:IssueTime>13:58:10+02:00</cbc:IssueTime><!--BT-757-notice (Order: 13)--><cbc:VersionID>01</cbc:VersionID><!--BT-738-notice (Order: 16)--><cbc:RequestedPublicationDate>2025-08-04+02:00</cbc:RequestedPublicationDate><!--BT-01-notice (Order: 18)--><cbc:RegulatoryDomain>32014L0025</cbc:RegulatoryDomain><!--BT-02-notice (Order: 19)--><cbc:NoticeTypeCode listName="cont-modif">can-modif</cbc:NoticeTypeCode><!--BT-702(a)-notice (Order: 21)--><cbc:NoticeLanguageCode>DEU</cbc:NoticeLanguageCode><cac:ContractingParty><cac:Party><cac:PartyIdentification><!--OPT-300-Procedure-Buyer (Order: 02)--><cbc:ID schemeName="organization">ORG-0001</cbc:ID></cac:PartyIdentification><cac:ServiceProviderParty><cbc:ServiceTypeCode listName="organisation-role">ted-esen</cbc:ServiceTypeCode><cac:Party><cac:PartyIdentification><cbc:ID schemeName="organization">ORG-0004</cbc:ID></cac:PartyIdentification></cac:Party></cac:ServiceProviderParty></cac:Party></cac:ContractingParty><cac:TenderingTerms><cac:ProcurementLegislationDocumentReference><cbc:ID>sektvo</cbc:ID></cac:ProcurementLegislationDocumentReference></cac:TenderingTerms><cac:ProcurementProject><!--BT-22-Procedure (Order: 02)--><cbc:ID>23FEI70722</cbc:ID><!--BT-21-Procedure (Order: 03)--><cbc:Name languageID="DEU">Bauleistungen Kabeltiefbau ESTW Schirnding</cbc:Name><!--BT-24-Procedure (Order: 04)--><cbc:Description languageID="DEU">Das Projekt im auszurüstenden Streckenabschnitt der Strecke 5903 zwischen Markt-redwitz(a) und Landesgrenze, km 125,468 – km 140,587, ist eine Maßnahme zur Um-setzung der Anforderungen an Strecken des TEN-Streckennetzes. Maßgebendes Ziel in der 1. Baustufe ist die Ausstattung des Streckenbereiches mit ETCS L2mS nach BTFS3 V3.0 inkl. Transition zum Nachbarland CZ. Bedingt dadurch ist ein Ersatz des bestehenden SpDr S60-Stellwerkes in Schirnding zum ESTW-A mit Anbindung an die ESTW-Z Marktredwitz notwendig.
Die Inbetriebnahme für das Stellwerk ESTW-A in Schirnding ist voraussichtlich im März 2024, gefolgt von der Inbetriebnahme ETCS im Dezember 2025.

Gegenstand der Vergabe sind Kabeltiefbauleistungen als Haupt- und Nebenbauleis-tungen für das unter Punkt I beschriebenes Projekt. Die Leistungen bestehen aus:
• das Herstellen von Kabelkanälen → ca. 21 km
• das Herstellen von Querungen → ca. 33 Stück
• das Gründen von Signalfundamenten → ca. 38 Stück
• Kabelverlegung → ca. 31,5 km
• Schwellentausch → ca. 120 Stück</cbc:Description><!--BT-23-Procedure (Order: 05)--><cbc:ProcurementTypeCode listName="contract-nature">works</cbc:ProcurementTypeCode><!--BT-300-Procedure (Order: 12)--><cbc:Note languageID="DEU">Folgende Erklärungen sind im Offenen Verfahren mit dem Angebot und bei einem Aufruf zum Teilnahmewettbewerb mit dem Teilnahmeantrag abzugeben. Zusätzliche Unterlagen sind nicht erwünscht:


Die interessierten Wirtschaftsteilnehmer müssen dem Auftraggeber mitteilen, dass sie an den Aufträgen interessiert sind; die Aufträge werden ohne spätere Veröffentlichung eines Aufrufs zum Wettbewerb vergeben.
Durch den Wirtschaftsteilnehmer sind als Teilnahmebedingung neben den zuvor genannten Erklärungen/Nachweisen folgende weitere Erklärungen/Nachweise erforderlich:
1. Erklärung, ob und inwieweit mit dem/den vom AG beauftragten Ingenieurbüro(s) Verbundenheit (gesellschaftsrechtlich verbunden im Sinne § 18 AktG / verwandtschaftliche Beziehungen zwischen Organen des Bieters und Organen des Ingenieurbüros) oder wirtschaftliche Abhängigkeit besteht. Bei Bietergemeinschaften gilt, dass jedes einzelne Mitglied eine entsprechende Erklärung abzugeben hat.
Beauftragte(s) Ingenieurbüro(s):
1.	  DB Engineering &amp; Consulting GmbH   
2.	  PTB - Ingenieurbüro für Planung, Technologie und Bauüberwachung Magdeburg GmbH  
3.	  DB Kommunikationstechnik GmbH
4.       Obermeyer Infrastruktur GmbH &amp; Co. KG
5.       INeTEC GmbH
6.       DB Bahnbaugruppe GmbH

Der Auftraggeber behält sich vor, Angebote von Bietern auszuschließen, die unter Mitwirkung eines vom Auftraggeber beauftragten Ingenieurbüros erstellt wurden. Gleiches gilt, wenn zwischen Bieter und beauftragtem Ingenieurbüro eine gesellschaftsrechtliche/verwandtschaftliche Verbundenheit oder wirtschaftliche Abhängigkeit besteht.

Fragen zu den Vergabeunterlagen oder dem Vergabeverfahren sind so rechtzeitig zu stellen, dass dem Auftraggeber unter Berücksichtigung interner Abstimmungsprozesse eine Beantwortung spätestens sechs Tage vor Ablauf der Frist zur Angebotsabgabe bzw. zur Einreichung der Teilnahmeanträge möglich ist. Der Auftraggeber behält sich vor, nicht rechtzeitig gestellte Fragen gar nicht oder innerhalb von weniger als sechs Tagen vor Ablauf der Frist zur Angebotsabgabe bzw. zur Einreichung der Teilnahmeanträge zu beantworten.

Der Auftraggeber behält sich die Anwendung von §§ 123, 124 GWB vor.

Bei Durchführung eines Verhandlungsverfahrens behält sich der Auftraggeber die Möglichkeit vor, den Auftrag auf der Grundlage der Erstangebote zu vergeben, ohne in Verhandlungen einzutreten. Für den Fall, dass die Bieter im Rahmen einer Verhandlung zur Abgabe eines preislich modifizierten Angebots aufgefordert werden, behält das Angebot der 1. Angebotseröffnung einschl. der Nebenangebote weiterhin Gültigkeit. Das gilt sowohl für den Fall, dass der Bieter fristgemäß ein modifiziertes Angebot vorlegt, als auch für den Fall, dass der Bieter ein modifiziertes Angebot nicht oder nicht fristgemäß vorlegt. Der Zuschlag wird auf das wirtschaftlichste Angebot (des Bestbieters) erteilt.

Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach § 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
Geforderte Kautionen und Sicherheiten:
Vertragserfüllungsbürgschaft
in Höhe von 5 v.H. der Auftragssumme


Geforderte Kautionen und Sicherheiten:
Bürgschaft für Mängelansprüche
in Höhe von 3 v.H. der Abrechnungssumme


Die Zahlungsbedingungen gelten gemäß Vergabeunterlagen.</cbc:Note><cac:MainCommodityClassification><!--BT-262-Procedure (Order: 05)--><cbc:ItemClassificationCode listName="cpv">45234100</cbc:ItemClassificationCode></cac:MainCommodityClassification><cac:RealizedLocation><cac:Address><!--BT-5131-Procedure (Order: 20)--><cbc:CityName>Arzberg</cbc:CityName><!--BT-5121-Procedure (Order: 21)--><cbc:PostalZone>95659</cbc:PostalZone><!--BT-5071-Procedure (Order: 23)--><cbc:CountrySubentityCode listName="nuts">DE24D</cbc:CountrySubentityCode><cac:Country><!--BT-5141-Procedure (Order: 02)--><cbc:IdentificationCode listName="country">DEU</cbc:IdentificationCode></cac:Country></cac:Address></cac:RealizedLocation></cac:ProcurementProject><cac:ProcurementProjectLot><!--BT-137-Lot (Order: 02)--><cbc:ID schemeName="Lot">LOT-0001</cbc:ID><cac:TenderingTerms><ext:UBLExtensions><ext:UBLExtension><ext:ExtensionContent><efext:EformsExtension><efac:StrategicProcurement><!--BT-717-Lot (Order: 01)--><efbc:ApplicableLegalBasis listName="cvd-scope">false</efbc:ApplicableLegalBasis></efac:StrategicProcurement></efext:EformsExtension></ext:ExtensionContent></ext:UBLExtension></ext:UBLExtensions><!--BT-60-Lot (Order: 09)--><cbc:FundingProgramCode listName="eu-funded">no-eu-funds</cbc:FundingProgramCode><!--BT-94-Lot (Order: 18)--><cbc:RecurringProcurementIndicator>false</cbc:RecurringProcurementIndicator><cac:PaymentTerms><!--BT-77-Lot (Order: 05)--><cbc:Note languageID="DEU">Die Zahlungsbedingungen gelten gemäß Vergabeunterlagen.</cbc:Note></cac:PaymentTerms><cac:TendererQualificationRequest><!--BT-761-Lot (Order: 02)--><cbc:CompanyLegalFormCode listName="required">false</cbc:CompanyLegalFormCode></cac:TendererQualificationRequest><cac:ContractExecutionRequirement><!--BT-736-Lot (Order: 03)--><cbc:ExecutionRequirementCode listName="reserved-execution">no</cbc:ExecutionRequirementCode></cac:ContractExecutionRequirement><cac:ContractExecutionRequirement><!--OPT-060-Lot (Order: )--><cbc:ExecutionRequirementCode listName="conditions">performance</cbc:ExecutionRequirementCode><!--BT-70-Lot (Order: 04)--><cbc:Description languageID="DEU">Entfällt</cbc:Description></cac:ContractExecutionRequirement><cac:ContractExecutionRequirement><!--BT-743-Lot (Order: 03)--><cbc:ExecutionRequirementCode listName="einvoicing">required</cbc:ExecutionRequirementCode></cac:ContractExecutionRequirement><cac:AdditionalInformationParty><cac:PartyIdentification><!--OPT-301-Lot-AddInfo (Order: 02)--><cbc:ID schemeName="organization">ORG-0001</cbc:ID></cac:PartyIdentification></cac:AdditionalInformationParty><cac:AppealTerms><cac:PresentationPeriod><!--BT-99-Lot (Order: 08)--><cbc:Description languageID="DEU">Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach § 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.</cbc:Description></cac:PresentationPeriod><cac:AppealInformationParty><cac:PartyIdentification><!--OPT-301-Lot-ReviewInfo (Order: 02)--><cbc:ID schemeName="organization">ORG-0002</cbc:ID></cac:PartyIdentification></cac:AppealInformationParty><cac:AppealReceiverParty><cac:PartyIdentification><!--OPT-301-Lot-ReviewOrg (Order: 02)--><cbc:ID schemeName="organization">ORG-0002</cbc:ID></cac:PartyIdentification></cac:AppealReceiverParty></cac:AppealTerms><cac:PostAwardProcess><!--BT-92-Lot (Order: 04)--><cbc:ElectronicOrderUsageIndicator>true</cbc:ElectronicOrderUsageIndicator><!--BT-93-Lot (Order: 05)--><cbc:ElectronicPaymentUsageIndicator>true</cbc:ElectronicPaymentUsageIndicator></cac:PostAwardProcess></cac:TenderingTerms><cac:TenderingProcess><!--BT-115-Lot (Order: 13)--><cbc:GovernmentAgreementConstraintIndicator>true</cbc:GovernmentAgreementConstraintIndicator><cac:ContractingSystem><!--BT-765-Lot (Order: 03)--><cbc:ContractingSystemTypeCode listName="framework-agreement">none</cbc:ContractingSystemTypeCode></cac:ContractingSystem></cac:TenderingProcess><cac:ProcurementProject><!--BT-22-Lot (Order: 02)--><cbc:ID>e4e1e2b2-5227-497b-9373-693a1e713895</cbc:ID><!--BT-21-Lot (Order: 03)--><cbc:Name languageID="DEU">Bauleistungen Kabeltiefbau ESTW Schirnding</cbc:Name><!--BT-24-Lot (Order: 04)--><cbc:Description languageID="DEU">Das Projekt im auszurüstenden Streckenabschnitt der Strecke 5903 zwischen Markt-redwitz(a) und Landesgrenze, km 125,468 – km 140,587, ist eine Maßnahme zur Um-setzung der Anforderungen an Strecken des TEN-Streckennetzes. Maßgebendes Ziel in der 1. Baustufe ist die Ausstattung des Streckenbereiches mit ETCS L2mS nach BTFS3 V3.0 inkl. Transition zum Nachbarland CZ. Bedingt dadurch ist ein Ersatz des bestehenden SpDr S60-Stellwerkes in Schirnding zum ESTW-A mit Anbindung an die ESTW-Z Marktredwitz notwendig.
Die Inbetriebnahme für das Stellwerk ESTW-A in Schirnding ist voraussichtlich im März 2024, gefolgt von der Inbetriebnahme ETCS im Dezember 2025.

Gegenstand der Vergabe sind Kabeltiefbauleistungen als Haupt- und Nebenbauleis-tungen für das unter Punkt I beschriebenes Projekt. Die Leistungen bestehen aus:
• das Herstellen von Kabelkanälen → ca. 21 km
• das Herstellen von Querungen → ca. 33 Stück
• das Gründen von Signalfundamenten → ca. 38 Stück
• Kabelverlegung → ca. 31,5 km
• Schwellentausch → ca. 120 Stück</cbc:Description><!--BT-23-Lot (Order: 05)--><cbc:ProcurementTypeCode listName="contract-nature">works</cbc:ProcurementTypeCode><!--BT-300-Lot (Order: 12)--><cbc:Note languageID="DEU">Für folgende Leistungen muss das für die Ausführung vorgesehene Unternehmen in einem Präqualifikationsverfahren bei der Deutschen Bahn AG präqualifiziert sein. Eine dementsprechende Erklärung ist im Offenen Verfahren mit dem Angebot und bei einem Aufruf zum Teilnahmewettbewerb mit dem Teilnahmeantrag abzugeben. Zusätzliche Unterlagen sind nicht erwünscht. Angaben zu den Teilnahmebedingungen und zum Präqualifikationsverfahren sind den Bewerbungsbedingungen Ziff. 17 und Besonderen Vertragsbedingungen zu entnehmen:

Bauleistung für Kabel: Kabelführungssysteme incl. Tiefbau

Bauleistung für Kabel: Kabelverlegung

Bauleistung für Kabel: Bauleistungen für Kabel–Bauen unter Eisenbahnbetrieb</cbc:Note><cac:ProcurementAdditionalType><!--BT-06-Lot (Order: 02)--><cbc:ProcurementTypeCode listName="strategic-procurement">none</cbc:ProcurementTypeCode></cac:ProcurementAdditionalType><cac:MainCommodityClassification><!--BT-262-Lot (Order: 05)--><cbc:ItemClassificationCode listName="cpv">45234100</cbc:ItemClassificationCode></cac:MainCommodityClassification><cac:RealizedLocation><cac:Address><!--BT-5131-Lot (Order: 20)--><cbc:CityName>Arzberg</cbc:CityName><!--BT-5121-Lot (Order: 21)--><cbc:PostalZone>95659</cbc:PostalZone><!--BT-5071-Lot (Order: 23)--><cbc:CountrySubentityCode listName="nuts">DE24D</cbc:CountrySubentityCode><cac:Country><!--BT-5141-Lot (Order: 02)--><cbc:IdentificationCode listName="country">DEU</cbc:IdentificationCode></cac:Country></cac:Address></cac:RealizedLocation><cac:PlannedPeriod><!--BT-536-Lot (Order: 02)--><cbc:StartDate>2024-04-29+02:00</cbc:StartDate><!--BT-537-Lot (Order: 04)--><cbc:EndDate>2025-09-19+02:00</cbc:EndDate></cac:PlannedPeriod><cac:ContractExtension><!--BT-58-Lot (Order: 04)--><cbc:MaximumNumberNumeric>0</cbc:MaximumNumberNumeric></cac:ContractExtension></cac:ProcurementProject></cac:ProcurementProjectLot><cac:TenderResult><!--OPT-999 (Order: 06)--><cbc:AwardDate>2024-04-22+02:00</cbc:AwardDate></cac:TenderResult></ContractAwardNotice>