Modification of a contract/concession during its term
Legal Basis:
Directive 2014/25/EU
Section I: Contracting authority/entity
Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
S21, PFA 1.3a, VE 10-Light Los 1 Rohbau, 18FEI32068, AVL-L1-014
Reference number: 2019/S 158-363200
II.1.2)Main CPV code45223220 Structural shell work
II.1.3)Type of contractWorks
II.2)Description
II.2.1)Title:
S21, PFA 1.3a, VE 10-Light Los 1 Rohbau
II.2.3)Place of performanceNUTS code: DE11 Stuttgart
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 15/10/2019
Section IV: Procedure
IV.2)Administrative information
IV.2.1)Contract award notice concerning this contract Section V: Award of contract/concession
Title:
S21, PFA 1.3a, VE 10-Light Los 1 Rohbau
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code45223220 Structural shell work
VII.1.3)Place of performanceNUTS code: DE11 Stuttgart
VII.1.4)Description of the procurement:
Im Zuge der Erstellung der vorgezogenen Ausführungsplanung im Bereich des Baches Koppenklinge wurde die Realisierung eines Provisoriums für die bauzeitliche Bachverlegung erforderlich um in dessen Schutz das endgültige Bauwerk der EÜ/WÜ Koppenthalklinge im Rahmen der Baumaßnahmen realisieren zu können.
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 20/04/2020
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)Total value of the contract/lot/concession: 1.00 EUR
VII.1.7)Name and address of the contractor/concessionaireOfficial name: ARGE Flughafentunnel c/o Ed.Züblin AG, Direktion IU-Tunnelbau
Postal address: Albstadtweg 5
Town: Stuttgart
NUTS code: DE11 Stuttgart
Postal code: 70567
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.2)Reasons for modificationNeed for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b) of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
Eine Herstellung des Geschiebeschutzgitters muss kurzfristig erfolgen und ist mit den Hauptbaumaßnahmen zu koordinieren. Dies erfordert eine Realisierung der Maßnahme durch die ARGE FHT. Die Integration eines weiteren Unternehmers innerhalb des begrenzten Baufeldes ist aufgrund des erforderlichen Koordinationsaufwandes und der notwendigen Kurzfristigkeit nicht möglich.
VII.2.3)Increase in priceUpdated total contract value before the modifications (taking into account possible earlier contract modifications and price adaptions and, in the case of Directive 2014/23/EU, average inflation in the Member State concerned)
Value excluding VAT: 393 017 977.50 EUR
Total contract value after the modifications
Value excluding VAT: 393 017 978.50 EUR