The following activities are included in the scope of the implementation of each step, namely ‘Rasovo’ and ‘Nova Province’, the following activities:
— Exploration for and provision of the necessary output data,
— Hydrological, geological and hydro-geological studies only for stage A New Provadia,
— Development of investment projects at the ‘Technical design phase’,
— Vote on the technical projects by the contracting authority, the consultant under Article 166 (1) of the Spatial Planning Act (ZUT), the competent control authorities, the operating companies and any other interested party,
— Approval of technical projects and production of building permits,
— Pre-detection of building sites — development of a ‘Safety and Health Plan (CKD) and Construction Waste Management Plan (PPCB) and approval under the SPA,
— Processing of the documentation of the properties concerned in the construction and rescue, archaeological surveys, the identification of owners or users/tenants of land, the establishment of the amount of the benefits for destroyed land and/or loss of land and/or damage during construction and/or rescue archaeological surveys, according to market assessments by a licensed independent valuer (agreed by the contracting authority) and performance of the compensation procedures, in accordance with the provisions of the Energy Act (ZE), the Cultural Heritage Act (ZCN) and the ZUT, which are paid by the contracting authority,
— Implementation of investment projects in the ‘Work Project’ phase,
— the composition of the work projects by the contracting authority, the consultant under Article 166 (1) of the Spatial Planning Act (ZUT), the competent control authorities, the operating companies and any other interested party,
— Suspension work, including renting of land, construction of temporary equEntity bases, provision of temporary power supplies and other temporary connections and communications, mobilisation and demobilisation, etc.,
— Supply of the necessary materials and equipment, spare parts, special tools and attachments, accompanied by the relevant documentation,
Construction, construction,
Exercise of designer’s supervision during the construction process,
Test: single, complex and host tests,
Drawing up the construction, executive and execution of the execution of the works,
— Cadastral photography and production of certificates under Article 54a (3) of the Land Register Act (ZZR),
— Signing of statements of findings establishing the fitness for acceptance of the work (Template 15) for the relevant stages,
— Adoption and entry into service activities at each stage: participation in committee for 72-hour samples at operational conditions and signature of a 72-hour sample for operating conditions (Model 17); advance agreed use of the use at each stage; participation in committee for the signing of Protocol (s) to establish the suitability for use of the work (Model 16) and assistance with obtaining authorisations to use the stages,
— Training of staff of the contracting authority.
According to the “Rasovo” AC, 3 numbers of YPTs in configuration 2 are to be installed in configuration of the number of operated GTTMs and 1 spare GTKA units with a nominal capacity of 12 MW each.
In configuration ‘Nova Province’, 4 GHTCA counts are foreseen in configuration 3, in configuration the number of employees, and 1 in nominal capacity, with a nominal capacity of 10 MW each.
In order to implement the interconnection of each of the phases to the transmission network of Bulgartransgaz EAD, it is planned to design and build an input and output loop and an optical cable line, and to connect them to the networks of technical infrastructure — design and construction of road connections, electricity supply, water and sanitation, etc.
The scope and requirements are detailed in the Technical Specifications and its annexes, part of the tender documentation.