Modification of a contract/concession during its term
Legal Basis:
Directive 2014/25/EU
Section I: Contracting authority/entity
I.1)Name and addressesOfficial name: DB Station & Service AG (Bukr. 11)
Town: Leipzig
NUTS code:
DED51 Leipzig, Kreisfreie StadtCountry: Germany
Contact person: Deutsche Bahn AG vertreten durch Beschaffung Infrastruktur, Region Südost (FS.EI-SO), Salomonstraße 21, 04103 Leipzig
E-mail:
anke.winzer@deutschebahn.comInternet address(es): Main address:
http://deutschebahn.com/bieterprotal Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
Umbau Verkehrsstation Stendal und Rückbau Röxer Tunnel Bauüberwachung
Reference number: 18GEI31418
II.1.2)Main CPV code71247000 Supervision of building work
II.1.3)Type of contractServices
II.2)Description
II.2.1)Title:
Umbau Verkehrsstation Stendal und Rückbau Röxer Tunnel Bauüberwachung
II.2.3)Place of performanceNUTS code: DEE0D Stendal
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 03/12/2018
End: 30/09/2022
Section IV: Procedure
IV.2)Administrative information
IV.2.1)Contract award notice concerning this contract Section V: Award of contract/concession
Title:
Umbau Verkehrsstation Stendal und Rückbau Röxer Tunnel Bauüberwachung
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code71247000 Supervision of building work
VII.1.3)Place of performanceNUTS code: DEE0A Mansfeld-Südharz
VII.1.4)Description of the procurement: VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 27/03/2021
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
VII.1.7)Name and address of the contractor/concessionaireOfficial name: DB Engineering & Consulting GmbH
Town: Leipzig
NUTS code: DED5 Leipzig
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.2)Reasons for modificationNeed for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b) of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
Der Wiederaufbau der Dächer konnte nicht in den ursprünglich vorgesehenen Sperrpausen erfolgen. Daher wurden gesonderte Sperrpausen beantragt. Ein Wechsel des AN würde zu erheblichen Problemen führen hinsichtlich der Schnittstellen in der Gesamtabwicklung.
VII.2.3)Increase in price