Framework agreement for rock protection in tunnels in the Rogaland area and in parts of Vestland County. The contract will mainly be based on the execution of shortcomings and errors after geological main inspections, which will be available before each measure.
Most of the work will be protection with bolts and concrete in tunnels, there will also be
the removal of netting/sheet arching/PE foam and scanning as required. There can be minor amounts of blasting/pigging. The contract will be for one year, contract 2023-2024, in which Mastrafjord, Byfjord, Håklepp, and Bømlafjord tunnels are to be improved in accordance with the main inspections, see the annex. The reports for Mastrafjord and Byfjord tunnels are completed, whilst the reports for Håklepp and Bømlafjord tunnels are being prepared.
The scope of the framework agreement for 2023-2024 is estimated to be NOK 30 million excluding VAT. Further scopes are dependent on allocations. The maximum turnover for the framework agreement is estimated to be NOK 120 million excluding VAT for the entire contract period, including the options (1+1+1). The contract can be extended for one year at a time to a total length of maximum 4 years 2023-2027. This is basically governed by the budget and need.
The scopes and processes can vary in the option years in accordance with the contract.
Option: The parties can mutually agree to extend the contract for a further 1 year at a time, to a total contract length of 4 years. A decision will be made in the last week in March each year as to whether the option will be taken up.