Modification of a contract/concession during its term
Legal Basis:
Directive 2014/25/EU
Section I: Contracting authority/entity
Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
Bauüberwachungsleistungen 4 EÜ auf der Strecke 6343 und 1 EÜ auf der Strecke 6340
Reference number: 18GEI33169
II.1.2)Main CPV code71521000 Construction-site supervision services
II.1.3)Type of contractServices
II.2)Description
II.2.1)Title:
Bauüberwachungsleistungen 4 EÜ auf der Strecke 6343 und 1 EÜ auf der Strecke 6340
II.2.3)Place of performanceNUTS code: DEE0A Mansfeld-Südharz
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 01/12/2018
End: 30/11/2019
Section IV: Procedure
IV.2)Administrative information
IV.2.1)Contract award notice concerning this contract Section V: Award of contract/concession
Title:
Bauüberwachungsleistungen 4 EÜ auf der Strecke 6343 und 1 EÜ auf der Strecke 6340
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code71521000 Construction-site supervision services
VII.1.3)Place of performanceNUTS code: DEE0A Mansfeld-Südharz
VII.1.4)Description of the procurement:
Erstellung des SiGe Planes während der Planungsphase.
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 08/08/2019
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
VII.1.7)Name and address of the contractor/concessionaireOfficial name: DB Engineering & Consulting Gmb
Town: Leipzig
NUTS code: DED5 Leipzig
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.2)Reasons for modificationNeed for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b) of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
a) SiGe Plan ist gemäß Baustellenverordnung erforderlich und lag zu Vertragsbeginn zur Fortschreibung gem. Vertrag nicht vor;
b) Fortschreibung des Planes bereits vertraglich gebunden;
d) Zeitverzug durch Bindung neuer Kapazitäten.
VII.2.3)Increase in price