Modification of a contract/concession during its term
Legal Basis:
Directive 2014/25/EU
Section I: Contracting authority/entity
Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
18GEI33660 Erneuerung EÜ km 64,753 in Neukirchen und EÜ km 72,228 in Werdau Strecke 6362 Leipzig-Connewitz – Hof
Reference number: 18GEI33660
II.1.2)Main CPV code71320000 Engineering design services
II.1.3)Type of contractServices
II.2)Description
II.2.1)Title:
Erneuerung EÜ km 64,753 in Neukirchen und EÜ km 72,228 in Werdau Strecke 6362 Leipzig-Connewitz – Hof
II.2.3)Place of performanceNUTS code: DED45 Zwickau
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 15/10/2018
End: 31/12/2023
Section IV: Procedure
IV.2)Administrative information
IV.2.1)Contract award notice concerning this contract Section V: Award of contract/concession
Title:
Erneuerung EÜ km 64,753 in Neukirchen und EÜ km 72,228 in Werdau Strecke 6362 Leipzig-Connewitz – Hof
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code71320000 Engineering design services
VII.1.3)Place of performanceNUTS code: DED45 Zwickau
VII.1.4)Description of the procurement:
1. Erstellung dynamische Nachweise gem. TM 1-2019-10046I.NPF2 zu Ril 804 für die Vorzugsvariante der Vorplanung;
2. Erstellung zusätzlicher Bauablaufuntersuchungen zur Anpassung Bauablauf an die von der PD Zwickau vorgegebenen 3-monatigen Totalsperrung und zur Anpassung der Vorplanung an das Ergebnis der dynamischen Nachweise aus Pos. 1 (Brückenkonstruktion) sowie der Baugrunderkundungen (Tiefgründung statt Flachgründung);
3. Objektplanung Verkehrsanlage gemäß §47 i. V. m. Anlage 13 Lph. 4 HOAI.
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 31/08/2019
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
VII.1.7)Name and address of the contractor/concessionaireOfficial name: BPR Dr. Schäpertöns Consult GmbH & Co KG
Town: Berlin
NUTS code: DE30 Berlin
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.2)Reasons for modificationNeed for modification brought about by circumstances which a diligent contracting authority/entity could not foresee (Art. 43(1)(c) of Directive 2014/23/EU, Art. 72(1)(c) of Directive 2014/24/EU, Art. 89(1)(c) of Directive 2014/25/EU)
Description of the circumstances which rendered the modification necessary and explanation of the unforeseen nature of these circumstances:
b) Wechsel des AN ist aus wirtschaftlichen Gründen nicht möglich Zur Sicherstellung der geplanten Ausführungstermine ist ein Wechsel des AN nicht möglich. Der Synergieeffekt durch eine einheitliche Leistungsdurchführung und Leistungsbetreuung geht verloren.
d) Wechsel des AN ist mit erheblichen Schwierigkeiten oder Zusatzkosten verbunden Ein Wechsel des AN würde aufgrund der erforderlichen Einarbeitungszeit zur Verlängerung des Leistungszeitraums führen. Der Vergabetermin und letztlich Baubeginn werden gefährdet bzw. sind nicht sicherzustellen. Weiterhin würden honorarmindernde Faktoren und Synergieeffekte bei einer getrennten Vergabe wegfallen und somit beträchtliche Zusatzkosten entstehen.
VII.2.3)Increase in price