Works - 503785-2019

25/10/2019    S207

Germany-Stuttgart: Miscellaneous building structures

2019/S 207-503785

Modification notice

Modification of a contract/concession during its term

Legal Basis:
Directive 2014/25/EU

Section I: Contracting authority/entity

I.1)Name and addresses
Official name: Deutsche Bahn AG
National registration number: DE11
Postal address: Räpplenstraße 17
Town: Stuttgart
NUTS code: DE11 Stuttgart
Postal code: 70191
Country: Germany
Contact person: Deutsche Bahn AG – Beschaffung Infrastruktur FS.EI 3
E-mail: einkauf-s21nbs@deutschebahn.com
Fax: +49 69-265-21939
Internet address(es):
Main address: www.deutschebahn.com
Address of the buyer profile: http://www.deutschebahn.com/bieterportal

Section II: Object

II.1)Scope of the procurement
II.1.1)Title:

S21, PFA 1.6a; Los 2 B, Interregiokurve, Ingenieurbauwerke, NT 41

Reference number: 2018/S 119-271605
II.1.2)Main CPV code
44112000 Miscellaneous building structures
II.1.3)Type of contract
Works
II.2)Description
II.2.1)Title:

S21, PFA 1.6a; Los 2 b, Interregiokurve, Ingenieurbauwerke

Lot No: 2B
II.2.3)Place of performance
NUTS code: DE11 Stuttgart
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or concession
Start: 12/10/2017
End: 25/05/2020

Section IV: Procedure

IV.2)Administrative information
IV.2.1)Contract award notice concerning this contract
Notice number in the OJ S: 2019/S 011-022423

Section V: Award of contract/concession

Contract No: 18FEI33267
Lot No: Los 2b
Title:

S21, PFA 1.6a; Los 2 b Interregiokurve, Ingenieurbauwerke

Section VII: Modifications to the contract/concession

VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
44112000 Miscellaneous building structures
VII.1.3)Place of performance
NUTS code: DE11 Stuttgart
VII.1.4)Description of the procurement:

S21, PFA 1.6a; Los 2 B, Interregiokurve, Ingenieurbauwerke

VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or concession
Start: 01/02/2019
End: 31/12/2019
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
VII.2)Information about modifications
VII.2.2)Reasons for modification
Need for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b) of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:

Die gegenüber der ARGE zusätzlich geforderten Leistungen (Gleisbau Lückenschluss) sind für den vorgegebenen Erfolg (Nutzung Gleis 278 zum 15.12.2019) unbedingt erforderlich. Durch den laufenden Baustellenbetrieb des Hauptunternehmers (ARGE) lässt sich ein gesonderter Nachunternehmer nicht mehr in den Bauablauf integrieren. Erhebliche Mehrkosten aufgrund der aufgemachten Schnittstellen würden damit hervorgerufen. Die Einbindung eines weiteren Dritten (Fachfirma für Gleisbau) in den vereinbarten Bauablauf führt zu Mehrkosten aufgrund der damit geänderten Bauumstände des Hauptunternehmers.

VII.2.3)Increase in price