Lavori - 525242-2018

Unrevised Machine Translation

29/11/2018    S230    - - Works - Additional information - Open procedure 

Bulgaria-Sofia: Motorway construction works

2018/S 230-525242

Corrigendum

Notice for changes or additional information

Works

(Supplement to the Official Journal of the European Union, 2018/S 166-377887)

Legal Basis:

Directive 2014/24/EU

Section I: Contracting authority/entity

I.1)Name and addresses
Agentsiya „Patna infrastruktura“
000695089
bul. „Makedoniya“ No. 3
Sofiya
1606
Bulgaria
Contact person: Biserka Borisova/inzh. Bilyana Vlaeva/inzh. Ralitsa Popova
Telephone: +359 29173396
E-mail: b.s.borisova@api.bg
Fax: +359 29173398
NUTS code: BG411

Internet address(es):

Main address: www.api.bg

Address of the buyer profile: http://www.api.bg/PROXY/index2.php?/public/index.jsp?proc=1093

Section II: Object

II.1)Scope of the procurement
II.1.1)Title:

Identification of the design contractor (drafting of the technical design) and construction of the Struma Motorway, Lot 3.2.2, Kruk-Kresna section — left... (see Box II.1.4)

II.1.2)Main CPV code
45233110
II.1.3)Type of contract
Works
II.1.4)Short description:

The subject of public procurement (OP) is the identification of a design contractor (design of the technical design) and construction of the “Motorway” project, Lot 3.2.2, Krushta Kresna section — left of km 389 + 100 to km 399 + 500, Kresna bypass — a right piece of km 396 + 137 (on the track of I-1 (E79) to km 401 + 691,90 397 + 000 of Struma motorway, including road links). In this sense, the objective of the PO is for the RIA to commission the construction of the Struma motorway, Lot 3.2.2 and road connections in the section. The preliminary design of the major bridge structures is 49 000 m², their gauge is 11 m and 14 m, and the total approximate length of gear 3 600 m. the formation range from 17 m to 302 m. the construction of 4 tunnels varies from 2 000 m to m. the approximate length ranges from 171 m to 1 303 m. the design standards for roads of design for AM, I and II roads are 11,5 tonnes per axle.

Section VI: Complementary information

VI.5)Date of dispatch of this notice:
27/11/2018
VI.6)Original notice reference
Notice number in the OJ S: 2018/S 166-377887

Section VII: Changes

VII.1)Information to be changed or added
VII.1.2)Text to be corrected in the original notice
Section number: IV.2.2)
Place of text to be modified: Срок за получаване на оферти или на заявления за участие:
Instead of:
Date: 29/11/2018
Local time: 17:30
Read:
Date: 17/12/2018
Local time: 17:30
Section number: IV.2.7)
Place of text to be modified: Условия за отваряне на офертите:
Instead of:
Date: 30/11/2018
Local time: 14:00
Read:
Date: 18/12/2018
Local time: 14:00
VII.2)Other additional information: