Modification of a contract/concession during its term
Legal Basis:
Directive 2014/25/EU
Section I: Contracting authority/entity
Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
Planungsleistungen für Verkehrsstation Brachbach, Erhöhung Mittelbahnsteig/ Modernisierung; IBW Lph 5 und 6; 7; VA Lph 5, 6, 7; TWP 4, 5, 6 Lph
Reference number: 18FEI34823
II.1.2)Main CPV code71240000 Architectural, engineering and planning services
II.1.3)Type of contractServices
II.2)Description
II.2.2)Additional CPV code(s)71240000 Architectural, engineering and planning services
II.2.3)Place of performanceNUTS code: DEB13 Altenkirchen (Westerwald)
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 10/12/2018
End: 29/10/2019
Section IV: Procedure
IV.2)Administrative information
IV.2.1)Contract award notice concerning this contract Section V: Award of contract/concession
Title:
Planungsleistungen für Verkehrsstation Brachbach, Erhöhung Mittelbahnsteig/ Modernisierung; IBW Lph 5 und 6; 7; VA Lph 5, 6, 7; TWP 4, 5, 6 Lph
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code71240000 Architectural, engineering and planning services
VII.1.3)Place of performanceNUTS code: DEB13 Altenkirchen (Westerwald)
VII.1.4)Description of the procurement:
Planungsleistungen für Verkehrsstation Brachbach, Erhöhung Mittelbahnsteig/ Modernisierung; IBW Lph 5 und 6; 7; VA Lph 5, 6, 7; TWP 4, 5, 6 Lph
VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 10/12/2018
End: 29/10/2019
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
VII.2)Information about modifications
VII.2.2)Reasons for modificationNeed for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b) of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
Nach dem Einbau der Hilfsbrücke entstand zwischen dem Bestandsteil des Rahmenbauwerks der PU und dem Altbestand eine zusätzliche Lücke die mittels Übergangskonstruktion zwischen Gleis und Bahnsteigbereich geschlossen wurde. Zusätzlich musste für unterhalb der provisorischen Konstruktion ein Übergang geplant werden, welche die PU Decke und Hilfsbrückenunterbau (Träger) bündig schließt. Diese Konstruktion ist Gegenstand.
VII.2.3)Increase in price