Modification of a contract/concession during its term
Legal Basis:
Directive 2014/25/EU
Section I: Contracting authority/entity
Section II: Object
II.1)Scope of the procurement
II.1.1)Title:Reference number: 15TEI18302
II.1.2)Main CPV code45234160 Catenary's construction works
II.1.3)Type of contractWorks
II.2)Description
II.2.2)Additional CPV code(s)45234160 Catenary's construction works
II.2.3)Place of performanceNUTS code: DE929 Region Hannover
Main site or place of performance:
II.2.4)Description of the procurement at the time of conclusion of the contract: II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 16/02/2016
End: 31/12/2020
II.2.13)Information about European Union fundsThe procurement is related to a project and/or programme financed by European Union funds: no
Section V: Award of contract/concession
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:05/02/2016
V.2.2)Information about tendersThe contract/concession has been awarded to a group of economic operators: no
V.2.3)Name and address of the contractor/concessionaireOfficial name: Rail Power Systems GmbH
Town: München
NUTS code:
DE21K Rosenheim, LandkreisCountry: Germany
E-mail:
info@rail-ps.comTelephone: +49 8941999-0
Fax: +49 8941999-270
Internet address:
www.rail-ps.comThe contractor/concessionaire is an SME: no
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion of the contract;excluding VAT)Total value of the procurement: 4 155 704.00 EUR
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review bodyOfficial name: Bezeichnung: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedurePrecise information on deadline(s) for review procedures:
Genaue Angaben zu den Fristen für die Einlegung von Rechtsbehelfen: Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach § 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:18/01/2022
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code45234160 Catenary's construction works
VII.1.2)Additional CPV code(s)45234160 Catenary's construction works
VII.1.3)Place of performanceNUTS code: DE929 Region Hannover
Main site or place of performance:
VII.1.4)Description of the procurement: VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 16/02/2016
End: 31/12/2020
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)Total value of the contract/lot/concession: 4 155 704.00 EUR
VII.1.7)Name and address of the contractor/concessionaireOfficial name: Rail Power systems GmbH
Town: München
NUTS code: DE21K Rosenheim, Landkreis
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.1)Description of the modificationsNature and extent of the modifications (with indication of possible earlier changes to the contract):
A2 - 130
Grünschnittarbeiten im Bereich des Bf Osnabrück Po
VII.2.2)Reasons for modificationNeed for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b) of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
- Wechsel des AN ist nicht möglich, da die Aufwendungen im Zusammenhang mit dem Hauptvertrag stehen.
VII.2.3)Increase in priceUpdated total contract value before the modifications (taking into account possible earlier contract modifications and price adaptions and, in the case of Directive 2014/23/EU, average inflation in the Member State concerned)
Value excluding VAT: 4 291 704.00 EUR
Total contract value after the modifications
Value excluding VAT: 4 307 704.00 EUR