Modification of a contract/concession during its term
Legal Basis:
Directive 2014/25/EU
Section I: Contracting authority/entity
Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
ESTW Osnabrück - Herstellung eines Kabelweges zwischen den Lichtmasten auf dem Mittelbahnsteig Bohmte
Reference number: 16FEI23213
II.1.2)Main CPV code45317000 Other electrical installation work
II.1.3)Type of contractWorks
II.2)Description
II.2.1)Title:
ESTW Osnabrück - Herstellung eines Kabelweges zwischen den Lichtmasten auf dem Mittelbahnsteig Bohmte
Lot No: 1
II.2.2)Additional CPV code(s)31600000 Electrical equipment and apparatus
34632000 Railways traffic-control equipment
II.2.3)Place of performanceNUTS code: DE944 Osnabrück, Kreisfreie Stadt
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 27/05/2016
End: 31/12/2021
Section V: Award of contract/concession
Title:
ESTW Osnabrück - Herstellung eines Kabelweges zwischen den Lichtmasten auf dem Mittelbahnsteig Bohmt
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code45317000 Other electrical installation work
VII.1.3)Place of performanceNUTS code: DE944 Osnabrück, Kreisfreie Stadt
VII.1.4)Description of the procurement: VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 27/05/2016
End: 31/12/2021
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)Total value of the contract/lot/concession: 1.00 EUR
VII.1.7)Name and address of the contractor/concessionaireOfficial name: Rail Power Systems GmbH
Postal address: Garmischer Straße 35
Town: München
NUTS code: DE212 München, Kreisfreie Stadt
Postal code: 81373
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.2)Reasons for modificationNeed for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b) of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:
- Wechsel des AN ist nicht möglich, da sonst die IBN TK im Bereich Bahnsteig Bohmte gefährdet wäre.
VII.2.3)Increase in priceUpdated total contract value before the modifications (taking into account possible earlier contract modifications and price adaptions and, in the case of Directive 2014/23/EU, average inflation in the Member State concerned)
Value excluding VAT: 3 373 591.06 EUR
Total contract value after the modifications