Services - 370984-2021

21/07/2021    S139

Germany-Frankfurt-on-Main: Construction project management services

2021/S 139-370984

Modification notice

Modification of a contract/concession during its term

Legal Basis:
Directive 2014/25/EU

Section I: Contracting authority/entity

I.1)Name and addresses
Official name: DB Netz AG (Bukr 16)
Postal address: Adam-Riese-Straße 11-13
Town: Frankfurt am Main
NUTS code: DE712 Frankfurt am Main, Kreisfreie Stadt
Postal code: 60327
Country: Germany
Contact person: Garbe, Markus
E-mail: markus.garbe@deutschebahn.com
Telephone: +49 89130872593
Fax: +49 69260913730
Internet address(es):
Main address: http://www.deutschebahn.com/bieterportal

Section II: Object

II.1)Scope of the procurement
II.1.1)Title:

2. S-Bahn-Stammstrecke München einschließlich netzergänzende Maßnahmen; Realisierungszentrum

Reference number: 18FEI32217
II.1.2)Main CPV code
71541000 Construction project management services
II.1.3)Type of contract
Services
II.2)Description
II.2.2)Additional CPV code(s)
71541000 Construction project management services
II.2.3)Place of performance
NUTS code: DE212 München, Kreisfreie Stadt
II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or concession
Start: 31/01/2019
End: 31/12/2019

Section IV: Procedure

IV.2)Administrative information
IV.2.1)Contract award notice concerning this contract
Notice number in the OJ S: 2019/S 059-137610

Section V: Award of contract/concession

Contract No: 18FEI32217
Title:

2. S-Bahn-Stammstrecke München einschließlich netzergänzende Maßnahmen; Realisierungszentrum

Section VII: Modifications to the contract/concession

VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code
71541000 Construction project management services
VII.1.3)Place of performance
NUTS code: DE212 München, Kreisfreie Stadt
VII.1.4)Description of the procurement:

Vom Auftragnehmer sind umfassende Projektmanagement- und Projektsteuerungsleistungen für das Großprojekt 2. S-Bahn-Stammstrecke inkl. netzergänzende Maßnahmen zu erbringen. Im einzelnen enthalten sind die Leistungsbereiche:

— Koordinierung und Qualitätsmanagement,

— Organisation/Dokumentation,

— Kostensteuerung und Kostenkontrolle,

— Terminsteuerung,

— Vertrags- und Nachtragsmanagement,

— Planlaufmanagement,

— Inbetriebnahmemanagement,

— Risikomanagement,

— Lean Management,

— fachtechnische Überwachung der Bauüberwachung/Baukoordination.

VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or concession
Start: 31/01/2019
End: 31/12/2019
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
VII.1.7)Name and address of the contractor/concessionaire
Official name: Schüßler-Plan Ingenieurgesellschaft mbH
Town: Frankfurt
NUTS code: DE712 Frankfurt am Main, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
VII.1.7)Name and address of the contractor/concessionaire
Official name: ILF Beratende Ingenieure GmbH
Town: München
NUTS code: DE212 München, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
VII.1.7)Name and address of the contractor/concessionaire
Official name: baustein GmbH
Town: München
NUTS code: DE212 München, Kreisfreie Stadt
Country: Germany
The contractor/concessionaire is an SME: no
VII.2)Information about modifications
VII.2.2)Reasons for modification
Need for additional works, services or supplies by the original contractor/concessionaire (Art. 43(1)(b) of Directive 2014/23/EU, Art. 72(1)(b) of Directive 2014/24/EU, Art. 89(1)(b) of Directive 2014/25/EU)
Description of the economic or technical reasons and the inconvenience or duplication of cost preventing a change of contractor:

Für die Erstellung der Ausschreibungsunterlagen sind vertiefte Kenntnisse des Projektes 2. S-Bahn-Stammstrecke München erforderlich, insbesondere deren terminliche und betriebliche Abhängigkeiten zueinander. Es handelt sich um direkt ineinandergreifende Arbeitsschritte zur Sicherstellung der erforderlichen Qualität der Ausschreibungsunterlagen. Die Leistung ist somit zwingend durch die bereits gebundene Projektsteuerung vorzunehmen.

Ein zusätzlicher AN muss sich durch mehrmonatige Einarbeitung umfangreiches Projektwissen aneignen, insbesondere hinsichtlich der Schittstellen zum Projekt 2. S-Bahn-Stammstrecke München, um die benötigte Leistung ausführen zu können. Dadurch entstehen erhebliche Verzögerungen im Leistungsablauf, die die enge Terminschiene weiter belasten.

VII.2.3)Increase in price