Envisaged options are as follows:
Option 1: Lift lobby doors I&C qualification;
Option 2: Port cell doors 46 doors (Design provided) I&C qualification;
Option 3: Lift lobby doors (4+4) I&C installation;
Option 4: Port cell doors 46 doors I&C installation:
Option 4.1: If Option 2 qualification fails, to remove the I&C installed and complete installation of all heavy nuclear doors;
Option 5: Qualification of I&C scope of confinement and shielding doors already installed:
Option 5.1: If Option 5 not valid, removal of components;
Option 6: Supply of four Additional lift lobby doors on hot cell building side.
Financial options
Option 7: Savings stemming from the release of Baseline 1 + Option 1 + Option 3;
Option 8: Savings stemming from the release of Baseline 1 + Option 1 + Option 3 + Option 6;
Option 9: Savings stemming from the release of Option 2 + Option 4;
Option 10: Savings stemming from the release of Option 2 + Option 4 + Option 4.1;
Option 11: Savings stemming from Baseline 2 + Option 5;
Option 12: Savings stemming from Baseline 2 + Option 5 + Option 5.1.