Modification of a contract/concession during its term
Legal Basis:
Directive 2014/25/EU
Section I: Contracting authority/entity
Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
Knoten Lindau Kabeltiefbau
Reference number: 17FEI30205
II.1.2)Main CPV code45200000 Works for complete or part construction and civil engineering work
II.1.3)Type of contractWorks
II.2)Description
II.2.2)Additional CPV code(s)45200000 Works for complete or part construction and civil engineering work
II.2.3)Place of performanceNUTS code: DE27A Lindau (Bodensee)
II.2.4)Description of the procurement at the time of conclusion of the contract: II.2.7)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 09/05/2018
End: 31/12/2021
II.2.13)Information about European Union fundsThe procurement is related to a project and/or programme financed by European Union funds: no
Section IV: Procedure
IV.2)Administrative information
IV.2.1)Contract award notice concerning this contract Section V: Award of contract/concession
Title:
Knoten Lindau Kabeltiefbau
V.2)Award of contract/concession
V.2.1)Date of conclusion of the contract/concession award decision:15/05/2018
V.2.2)Information about tenders
V.2.4)Information on value of the contract/lot/concession (at the time of conclusion of the contract;excluding VAT)
Section VI: Complementary information
VI.3)Additional information:
VI.4)Procedures for review
VI.4.1)Review bodyOfficial name: Vergabekammer des Bundes
Postal address: Villemomblerstr. 76
Town: Bonn
Postal code: 53123
Country: Germany
VI.4.3)Review procedurePrecise information on deadline(s) for review procedures:
Die Geltendmachung der Unwirksamkeit einer Auftragsvergabe in einem Nachprüfungsverfahren ist fristgebunden. Es wird auf die in § 135 Abs. 2 GWB genannten Fristen verwiesen. Nach § 135 Abs. 2 S. 2 GWB endet die Frist zur Geltendmachung der Unwirksamkeit 30 Kalendertage nach Veröffentlichung der Bekanntmachung der Auftragsvergabe im Amtsblatt der Europäischen Union. Nach Ablauf der jeweiligen Frist kann eine Unwirksamkeit nicht mehr festgestellt werden.
VI.5)Date of dispatch of this notice:04/11/2021
Section VII: Modifications to the contract/concession
VII.1)Description of the procurement after the modifications
VII.1.1)Main CPV code45200000 Works for complete or part construction and civil engineering work
VII.1.2)Additional CPV code(s)45200000 Works for complete or part construction and civil engineering work
VII.1.3)Place of performanceNUTS code: DE27A Lindau (Bodensee)
Main site or place of performance:
VII.1.4)Description of the procurement: VII.1.5)Duration of the contract, framework agreement, dynamic purchasing system or concessionStart: 09/05/2018
End: 31/12/2021
VII.1.6)Information on value of the contract/lot/concession (excluding VAT)
VII.2)Information about modifications
VII.2.1)Description of the modificationsNature and extent of the modifications (with indication of possible earlier changes to the contract):
251 - Das BMI hat mit Erlass vom 17.Juni 2020 (Az: BW I 7 - 70406/21#1) festgelegt, dass der Bund für seine Baumaßnahmen den
Bauunternehmen zur Abmilderung der Corona-Auswirkungen definierte Kostenerstattungen leistet, die mit der Einhaltung verschärfter
Hygiene- und Gesundheitsschutzmaßnahmen zusammenhängen.
VII.2.2)Reasons for modificationNeed for modification brought about by circumstances which a diligent contracting authority/entity could not foresee (Art. 43(1)(c) of Directive 2014/23/EU, Art. 72(1)(c) of Directive 2014/24/EU, Art. 89(1)(c) of Directive 2014/25/EU)
Description of the circumstances which rendered the modification necessary and explanation of the unforeseen nature of these circumstances:
Im Zusammenhang mit der Corona-Pandemie entstanden dem AN zusätzlichen Kosten bei der Bauausführung. Die erforderlichen
Nachweise (Rechnungen) wurden vom AN nicht erbracht bzw. dem Nachtrag nicht beigelegt, daher wurde die pauschale
Kostenerstattung (5 €/Ma und Tag) anerkannt.
VII.2.3)Increase in price