This contract will include, all relevant construction works, supplies for required plant, machinery, equipment and materials, installation, testing and commissioning
- The Yeniköy (Karacabey) WWTP will be constructed newly and the works will include construction of preliminary treatment units such as screens and aerated grit chamber; bio-P tank including chemical dosing system,, aeration andsedimentation tanks; disc filter and disinfection units; sludge dewatering units; and ancillary structures such as transformer, generator, and administration buildings. The WWTP capacity will be 4 400 m³/day.
- The existing capacity of Orhangazi WWTP is about 17000 m³/day and it is intended that capacity of the plant will be 51000 m³/day. The extension works for Orhangazi WWTP will include construction of preliminary treatment units such as screens and inlet pumping station; bio-P tank including chemical dosing system,, aeration and sedimentation tanks, RAS pumping station, Disc Filter, Disinfection Units, sludge dewatering units and ancillary structures such as blower, transformer and administration buildings.
- The extension works for İznik WWTP will include construction of the preliminary treatment units such as screens and aerated grit chamber, process units, rotary drum filter, anaerobic, anoxic (denitrification), membrane bio-recator(MBR) and treated water tanks; sludge dewatering units; ancillary structures such as transformer, generator, administration buildings. The existing capacity of İznik WWTP is about 9000 m³/day The final WWTP capacity will be 24000 m³/day.
The construction period will be 18 months, followed by 12 months for Defect Liability, guarantee, maintenance and operation period.